As written on the permit application.

To comply with nov#202302977. includes: repair foundation wall in the basement of the bldg including addition of foundation footings, installation new concrete wall at basement lv and upgrades to the wood structure including new posts, beams and addition of simpson strong wall sys.

Timeline
Key dates from the city record.
Filed
Nov 30, 2023
Issued
Jan 31, 2025 (14 months after filing)
Completed
Jul 10, 2025 (5 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
21 stops across 3 departments
Comments issued
7 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 7, 2023Administrative

Building inspector

Building Inspection · BID-INSP

Dec 5, 2023—

Building plan review

Building Inspection · BLDG

Dec 12, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Dec 11, 2023Approved

Permit Processing Center

Building Inspection · PPC

Jan 28, 2025Administrative

Building plan review

Building Inspection · BLDG

Feb 2, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jan 11, 2024Administrative

Structural plan approval

Building Inspection · PAD-STR

Jan 11, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Feb 2, 2024Approved

Fire prevention review

Fire Department · SFFD

Feb 2, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jun 5, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

May 22, 2024Approved

Fire prevention review

Fire Department · SFFD

Sep 24, 2024Administrative

Street use and mapping

Public Works · DPW-BSM

Jun 7, 2024Approved

Building plan review

Building Inspection · BLDG

Sep 12, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Sep 26, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Oct 24, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Nov 1, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jan 24, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Jan 27, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jan 31, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$1,600,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Darrel Wayne Harris

Hcg Associates, Inc.

EngineerS2433
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202311301718 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record