68 Haight St
San Francisco permit 202311301718 · Hayes Valley
To comply with nov#202302977. includes: repair foundation wall in the basement of the bldg including addition of foundation footings, installation new concrete wall at basement lv and upgrades to the wood structure including new posts, beams and addition of simpson strong wall sys.
- Filed
- Nov 30, 2023
- Issued
- Jan 31, 2025 (14 months after filing)
- Completed
- Jul 10, 2025 (5 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 21 stops across 3 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 30, 2023 | Dec 7, 2023 | Administrative |
Building inspector Building Inspection · BID-INSP | Dec 5, 2023 | Dec 5, 2023 | — |
Building plan review Building Inspection · BLDG | Dec 7, 2023 | Dec 12, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 7, 2023 | Dec 11, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 7, 2023 | Jan 28, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Dec 13, 2023 | Feb 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 11, 2024 | Jan 11, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jan 11, 2024 | Jan 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 17, 2024 | Feb 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 1, 2024 | Feb 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 14, 2024 | Jun 5, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 14, 2024 | May 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 14, 2024 | Sep 24, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 14, 2024 | Jun 7, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 6, 2024 | Sep 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 26, 2024 | Sep 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 24, 2024 | Oct 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 30, 2024 | Nov 1, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 23, 2025 | Jan 24, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 24, 2025 | Jan 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2025 | Jan 31, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,600,000
| Name | Role | License on permit |
|---|---|---|
| Darrel Wayne Harris Hcg Associates, Inc. | Engineer | S2433 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025