2350 Green St

San Francisco permit 202312011757 · Marina

New building (type unconfirmed)Full plan reviewIssued
Street view · Dec 2020
Google Street View of 2350 Green St, Dec 2020
Scope of work
As written on the permit application.

New structure is proposed to be an open private parking garage which locates on the merged lot 7 & lot 13 w/ a play yard above as an occupied roof.play yard is intended to accomodate students use during recess.property line adjustment app has been submitted.

Timeline
Key dates from the city record.
Filed
Dec 1, 2023
Issued
Jun 25, 2024 (7 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
90 stops across 7 departments
Comments issued
19 times, by Building Inspection, Fire Department, Public Works, Permit Center

Main permit

Review stopFinishedResult

Building inspector

Building Inspection · BID-INSP

Dec 1, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Dec 11, 2023Administrative

Zoning review

Planning · CP-ZOC

Feb 2, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jun 5, 2024Administrative

Building plan review

Building Inspection · BLDG

Mar 5, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 26, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 9, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 20, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 8, 2024Administrative

Fire prevention review

Fire Department · SFFD

Mar 1, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

May 30, 2024Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Mar 20, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Mar 11, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 26, 2024Approved

Building plan review

Building Inspection · BLDG

Apr 11, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 29, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 3, 2024Approved-Stipulated

Fire prevention review

Fire Department · SFFD

Apr 4, 2024Issued Comments

Building plan review

Building Inspection · BLDG

May 17, 2024Approved

Fire prevention review

Fire Department · SFFD

May 24, 2024Approved-Stipulated

Zoning review

Planning · CP-ZOC

May 14, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

May 22, 2024Approved

Street use and mapping

Public Works · DPW-BSM

May 24, 2024Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

May 30, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

May 16, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Jun 25, 2024Administrative

Addendum 1: Arch mep structural

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jul 12, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Jul 5, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Jul 5, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jul 12, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jul 23, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jul 23, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jul 26, 2024Administrative

Building plan review

Building Inspection · BLDG

Sep 6, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 20, 2024Approved

Fire prevention review

Fire Department · SFFD

Aug 26, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jul 31, 2024Administrative

Street use and mapping

Public Works · DPW-BSM

Jul 29, 2024Approved

Permit Processing Center

Building Inspection · PPC

Dec 17, 2024Administrative

Urban forestry

Public Works · DPW-BUF

Sep 11, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Aug 20, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Oct 23, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Oct 16, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 29, 2024Approved

Urban forestry

Public Works · DPW-BUF

Dec 3, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 15, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Oct 15, 2024Approved

Building plan review

Building Inspection · BLDG

Nov 25, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Nov 12, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 18, 2024Approved

Fire prevention review

Fire Department · SFFD

Nov 8, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Nov 12, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 14, 2024Administrative

Zoning review

Planning · CP-ZOC

Dec 16, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jan 29, 2025Administrative

Addendum 2: Fire sprinkler - reference pa#202507140698

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Mar 9, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Mar 10, 2026Administrative

Fire prevention review

Fire Department · SFFD

Mar 17, 2026Issued Comments

Permit Processing Center

Building Inspection · PPC

Mar 26, 2026Administrative

Fire prevention review

Fire Department · SFFD

Mar 19, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Mar 30, 2026Administrative

Addendum 3: Fire alarm

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Oct 6, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 7, 2025Administrative

Fire prevention review

Fire Department · SFFD

Dec 30, 2025Approved

Permit Processing Center

Building Inspection · PPC

Dec 31, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Dec 31, 2025Administrative

Addendum 4: Exterior enclosure

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Sep 22, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Sep 23, 2025Administrative

Zoning review

Planning · CP-ZOC

Oct 16, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 17, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Nov 17, 2025Approved

Fire prevention review

Fire Department · SFFD

Dec 3, 2025Approved

Public Health

HEALTH-MH

Sep 23, 2025Approved

Permit Processing Center

Building Inspection · PPC

Dec 3, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Dec 17, 2025Administrative

Addendum 5: Stairs

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Dec 12, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Dec 15, 2025Administrative

Building plan review

Building Inspection · BLDG

Feb 3, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Feb 5, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 4, 2026Not Applicable

Permit Processing Center

Building Inspection · PPC

Feb 19, 2026Administrative

Building plan review

Building Inspection · BLDG

Feb 19, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 19, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Feb 23, 2026Administrative

Addendum 6: Cable mesh

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Feb 12, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Feb 13, 2026Administrative

Building plan review

Building Inspection · BLDG

Feb 17, 2026Approved

Fire prevention review

Fire Department · SFFD

Feb 18, 2026Not Applicable

Permit Processing Center

Building Inspection · PPC

Feb 18, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

Feb 25, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$3,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Patricia G Alarcon

Ratcliff Architects

ArchitectC-27440
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202312011757 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record