2350 Green St
San Francisco permit 202312011757 · Marina
New structure is proposed to be an open private parking garage which locates on the merged lot 7 & lot 13 w/ a play yard above as an occupied roof.play yard is intended to accomodate students use during recess.property line adjustment app has been submitted.
- Filed
- Dec 1, 2023
- Issued
- Jun 25, 2024 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 90 stops across 7 departments
- Comments issued
- 19 times, by Building Inspection, Fire Department, Public Works, Permit Center
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Dec 1, 2023 | Dec 1, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 1, 2023 | Dec 11, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 11, 2023 | Feb 2, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 11, 2023 | Jun 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 7, 2024 | Mar 5, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 7, 2024 | Mar 26, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 7, 2024 | Feb 9, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 7, 2024 | Feb 20, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 7, 2024 | Feb 8, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 23, 2024 | Mar 1, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Feb 23, 2024 | May 30, 2024 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2024 | Mar 20, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 23, 2024 | Mar 11, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2024 | Feb 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 29, 2024 | Apr 11, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 29, 2024 | Mar 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2024 | Apr 3, 2024 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Apr 4, 2024 | Apr 4, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 13, 2024 | May 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 13, 2024 | May 24, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | May 13, 2024 | May 14, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 13, 2024 | May 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 13, 2024 | May 24, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | May 13, 2024 | May 30, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2024 | May 16, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 5, 2024 | Jun 25, 2024 | Administrative |
Addendum 1: Arch mep structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 1, 2024 | Jul 12, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jul 5, 2024 | Jul 5, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 5, 2024 | Jul 5, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 12, 2024 | Jul 12, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 15, 2024 | Jul 23, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 23, 2024 | Jul 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 24, 2024 | Jul 26, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 26, 2024 | Sep 6, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 26, 2024 | Aug 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 26, 2024 | Aug 26, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 26, 2024 | Jul 31, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jul 26, 2024 | Jul 29, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 26, 2024 | Dec 17, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Jul 29, 2024 | Sep 11, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 20, 2024 | Aug 20, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 11, 2024 | Oct 23, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 11, 2024 | Oct 16, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 11, 2024 | Oct 29, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 11, 2024 | Dec 3, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2024 | Oct 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 11, 2024 | Oct 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 7, 2024 | Nov 25, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 7, 2024 | Nov 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2024 | Nov 18, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 7, 2024 | Nov 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2024 | Nov 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2024 | Nov 14, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 13, 2024 | Dec 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 17, 2024 | Jan 29, 2025 | Administrative |
Addendum 2: Fire sprinkler - reference pa#202507140698
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 5, 2026 | Mar 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 10, 2026 | Mar 10, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 10, 2026 | Mar 17, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 10, 2026 | Mar 26, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 19, 2026 | Mar 19, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 26, 2026 | Mar 30, 2026 | Administrative |
Addendum 3: Fire alarm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 30, 2025 | Oct 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 7, 2025 | Oct 7, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 7, 2025 | Dec 30, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 7, 2025 | Dec 31, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 31, 2025 | Dec 31, 2025 | Administrative |
Addendum 4: Exterior enclosure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 10, 2025 | Sep 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2025 | Sep 23, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 23, 2025 | Oct 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 23, 2025 | Nov 17, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 23, 2025 | Nov 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 23, 2025 | Dec 3, 2025 | Approved |
Public Health HEALTH-MH | Sep 23, 2025 | Sep 23, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 23, 2025 | Dec 3, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 3, 2025 | Dec 17, 2025 | Administrative |
Addendum 5: Stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 24, 2025 | Dec 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 15, 2025 | Dec 15, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Dec 15, 2025 | Feb 3, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 15, 2025 | Feb 5, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 15, 2025 | Feb 4, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Dec 15, 2025 | Feb 19, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 19, 2026 | Feb 19, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 19, 2026 | Feb 19, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 19, 2026 | Feb 23, 2026 | Administrative |
Addendum 6: Cable mesh
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 27, 2026 | Feb 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2026 | Feb 13, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 13, 2026 | Feb 17, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 13, 2026 | Feb 18, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Feb 13, 2026 | Feb 18, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 18, 2026 | Feb 25, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $3,000,000
| Name | Role | License on permit |
|---|---|---|
| Patricia G Alarcon Ratcliff Architects | Architect | C-27440 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020