CheckMyDesigner

3321 Pierce St

San Francisco permit 202312011818 · Marina

Home remodel (type unconfirmed)Full plan reviewIssued
Street view · Jun 2016
Google Street View of 3321 Pierce St, Jun 2016
Scope of work
As written on the permit application.

Gr fl remodel (1) bathroom, create (1) new bathroom, relocate hallway, widening garage door and expand garage, eliminate main door. 2nd fl fireplace, guardrail @ deck, panoramic door. remove spiral staircase, remodel bath #3. 3rd fl no work.

Timeline
Key dates from the city record.
Filed
Jun 27, 2024
Issued
Sep 9, 2024 (2 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
51 stops across 5 departments
Comments issued
12 times, by Planning, Permit Center, Building Inspection, Public Works
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Dec 1, 2023Administrative

Zoning review

Planning · CP-ZOC

Dec 1, 2023Administrative

Intake

Building Inspection · INTAKE

Dec 13, 2023Administrative

Zoning review

Planning · CP-ZOC

Dec 14, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Dec 21, 2023Issued Comments

Intake

Building Inspection · INTAKE

Jan 31, 2024Administrative

Zoning review

Planning · CP-ZOC

Jan 31, 2024Issued Comments

Intake

Building Inspection · INTAKE

Feb 12, 2024Administrative

Zoning review

Planning · CP-ZOC

Feb 12, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 12, 2024Approved

Intake

Building Inspection · INTAKE

Mar 21, 2024Administrative

Zoning review

Planning · CP-ZOC

Apr 22, 2024Approved

Zoning review

Planning · CP-ZOC

Apr 22, 2024Approved

Building plan review

Building Inspection · BLDG

Apr 26, 2024Denied

Intake

Building Inspection · INTAKE

May 15, 2024Administrative

Zoning review

Planning · CP-ZOC

May 15, 2024Approved

Permit Center

Permit Center · PERMIT-CTR

May 30, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

May 23, 2024Not Applicable

Mechanical pre-screening

Building Inspection · PRE-MECH

May 29, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

May 30, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jun 12, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Jun 7, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Jun 7, 2024Not Applicable

Mechanical pre-screening

Building Inspection · PRE-MECH

Jun 10, 2024Approved

Permit Center

Permit Center · PERMIT-CTR

Jun 27, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Jun 18, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jun 20, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Jun 26, 2024Not Applicable

Central Permit Bureau

Building Inspection · CPB

Jun 27, 2024Administrative

Zoning review

Planning · CP-ZOC

Jul 1, 2024Approved

Building plan review

Building Inspection · BLDG

Jul 25, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 22, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 1, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 17, 2024Approved

Permit Processing Center

Building Inspection · PPC

Sep 4, 2024Administrative

Building plan review

Building Inspection · BLDG

Aug 14, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 15, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Aug 8, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Aug 9, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 8, 2024Approved

Building plan review

Building Inspection · BLDG

Aug 26, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 26, 2024Approved

Zoning review

Planning · CP-ZOC

Sep 3, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Aug 26, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 22, 2024Approved

Building plan review

Building Inspection · BLDG

Aug 28, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 4, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Aug 28, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 29, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Aug 29, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Sep 9, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$168,325
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Moses Shiuh Huang

Mha Consultant

EngineerC058502
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202312011818 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record