272 Wawona St
San Francisco permit 202312011823 · West of Twin Peaks
Vertical addition to add 2 bedroom and 1 bath.
- Filed
- Dec 1, 2023
- Issued
- Jan 2, 2025 (13 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 30 stops across 5 departments
- Comments issued
- 7 times, by Planning, Public Works, Building Inspection
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 1, 2023 | Dec 4, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 4, 2023 | Feb 23, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 4, 2023 | Dec 24, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jun 24, 2024 | Jun 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 25, 2024 | Jul 10, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2024 | Jun 26, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2024 | Jul 22, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 26, 2024 | Sep 16, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Nov 13, 2024 | Dec 23, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Nov 13, 2024 | Nov 13, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 13, 2024 | Nov 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 13, 2024 | Nov 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 13, 2024 | Nov 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 24, 2024 | Jan 2, 2025 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 9, 2024 | Jan 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2025 | Jan 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 28, 2025 | Jul 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 28, 2025 | Feb 28, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 28, 2025 | Feb 18, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2025 | Feb 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 28, 2025 | Jan 30, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 28, 2025 | Aug 8, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 30, 2025 | May 8, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 6, 2025 | May 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 18, 2025 | Jun 18, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 11, 2025 | Jul 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2025 | Jul 15, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2025 | Jul 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2025 | Aug 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2025 | Aug 28, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $180,000
| Name | Role | License on permit |
|---|---|---|
| Simon Kwan Kwan Design Architects Inc. | Architect | C27228 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2023