373 Chenery St
San Francisco permit 202312051919 · Glen Park
Replace and enlarge rear yard deck to including new firewall & infill lightwell, interior remodel (n) internal stair to second floor w/ rated wall at garage,replace/add windows, replace interior slab & foundation. kitchen, bathroom remodel w/o building area increase. replace/add windows.
- Filed
- Dec 5, 2023
- Issued
- Aug 21, 2024 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 27 stops across 5 departments
- Comments issued
- 6 times, by Planning, Building Inspection
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 5, 2023 | Dec 8, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 8, 2023 | Mar 29, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | May 16, 2024 | May 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 17, 2024 | May 31, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 27, 2024 | Jun 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 28, 2024 | Jul 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 2, 2024 | Jul 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 12, 2024 | Jul 18, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 22, 2024 | Jul 22, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 22, 2024 | Aug 21, 2024 | Administrative |
Addendum 1: Final-arch,t24,mech,elec, foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 17, 2024 | Oct 30, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 25, 2024 | Oct 25, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 25, 2024 | Oct 25, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Oct 28, 2024 | Oct 28, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 29, 2024 | Oct 29, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 31, 2024 | Nov 13, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 13, 2024 | Jan 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2024 | Jan 9, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 13, 2024 | Nov 15, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 13, 2024 | Apr 22, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jan 2, 2025 | Jan 10, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 24, 2025 | Jan 24, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 24, 2025 | Jan 31, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 24, 2025 | Feb 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2025 | Jan 30, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 21, 2025 | Apr 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2025 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $362,753
| Name | Role | License on permit |
|---|---|---|
| Andre Joel Rothblatt Rothblatt Architecture | Architect | C-22561 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025