As written on the permit application.

Replace and enlarge rear yard deck to including new firewall & infill lightwell, interior remodel (n) internal stair to second floor w/ rated wall at garage,replace/add windows, replace interior slab & foundation. kitchen, bathroom remodel w/o building area increase. replace/add windows.

Timeline
Key dates from the city record.
Filed
Dec 5, 2023
Issued
Aug 21, 2024 (9 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
27 stops across 5 departments
Comments issued
6 times, by Planning, Building Inspection

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 8, 2023Administrative

Zoning review

Planning · CP-ZOC

Mar 29, 2024Issued Comments

Zoning review

Planning · CP-ZOC

May 16, 2024Approved

Building plan review

Building Inspection · BLDG

May 31, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jun 28, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 1, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 9, 2024Approved

Zoning review

Planning · CP-ZOC

Jul 18, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jul 22, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Aug 21, 2024Administrative

Addendum 1: Final-arch,t24,mech,elec, foundation

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Oct 30, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Oct 25, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Oct 25, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Oct 28, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Oct 29, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Nov 13, 2024Administrative

Building plan review

Building Inspection · BLDG

Jan 15, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 9, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Nov 15, 2024Approved

Permit Processing Center

Building Inspection · PPC

Apr 22, 2025Administrative

Structural plan approval

Building Inspection · PAD-STR

Jan 10, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jan 24, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Jan 31, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 19, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 30, 2025Approved

Zoning review

Planning · CP-ZOC

Apr 21, 2025Approved

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$362,753
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Andre Joel Rothblatt

Rothblatt Architecture

ArchitectC-22561
Donald David

Double D Engineering

EngineerS3928
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202312051919 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record