Scope of work
As written on the permit application.

Int. & ext. alts: conv. part of garage to liv. space. remodel (e) kit. and 3 bdrms, 3 haths, powder rm, into 4 bdrms, 5 baths, 1 powder rm. all (n) interior finishes to replace (e) finishes. raise partial mansard roof to convert attic to 4th story. remove (e) window @ south facade. nfpa 13r sprkls

Timeline
Key dates from the city record.
Filed
Dec 7, 2023
Issued
Aug 26, 2024 (9 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 5 departments
Comments issued
8 times, by Building Inspection, Public Works
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Dec 7, 2023Administrative

Zoning review

Planning · CP-ZOC

Dec 12, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 12, 2023Approved

Permit Center

Permit Center · PERMIT-CTR

Dec 12, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Dec 19, 2023Administrative

Building plan review

Building Inspection · BLDG

Feb 7, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 6, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 9, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

May 7, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 13, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 23, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Apr 29, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jun 4, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jun 7, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 13, 2024Approved

Urban forestry

Public Works · DPW-BUF

Jun 29, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

Jul 2, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 3, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 18, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 22, 2024Approved

Zoning review

Planning · CP-ZOC

Jul 24, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jul 26, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Aug 26, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,296,380
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
John Taylor Hood

Hood Thomas Architects

ArchitectC-14187
Alexander Michael Santos

Altos Engineering

EngineerC-84144
Sources