4042 Fulton St #0
San Francisco permit 202312072116 · Outer Richmond
The scope of work is the add 1 adu to the storage area at the ground floor per sfpc 207(c)(4).
- Filed
- Dec 7, 2023
- Issued
- Aug 8, 2024 (8 months after filing)
- Completed
- Dec 1, 2025 (16 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 26 stops across 5 departments
- Comments issued
- 10 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 7, 2023 | Dec 13, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 14, 2023 | Apr 10, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 14, 2023 | Jan 10, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 14, 2023 | Feb 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 14, 2023 | Feb 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 14, 2023 | Feb 5, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 14, 2023 | Dec 19, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 14, 2023 | Dec 18, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 14, 2023 | Dec 15, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 14, 2023 | Jul 29, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 31, 2024 | Feb 2, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 8, 2024 | Feb 8, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 20, 2024 | Mar 15, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 27, 2024 | Feb 27, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 3, 2024 | Apr 19, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 22, 2024 | Apr 22, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 22, 2024 | Apr 26, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 22, 2024 | May 6, 2024 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Apr 24, 2024 | Apr 24, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 24, 2024 | Apr 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2024 | Apr 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2024 | Apr 29, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 18, 2024 | Jul 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 18, 2024 | Jul 18, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jul 19, 2024 | Jul 19, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 29, 2024 | Aug 8, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $175,000
| Name | Role | License on permit |
|---|---|---|
| Mark Kevin Hogan Openscope Studio | Architect | C33268 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025