32 Laidley St
San Francisco permit 202312072134 · Glen Park
A 3rd & 4th story addition to an existing 3 story home to include: (1) office, (1) full bath, (2) roof decks and a partial remodel of an existing bath.
- Filed
- Dec 7, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 15 stops across 5 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 7, 2023 | Dec 19, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 19, 2023 | Aug 28, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 19, 2023 | Dec 18, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 28, 2024 | Sep 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 28, 2024 | Sep 18, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 28, 2024 | Aug 28, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2024 | Sep 4, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 19, 2024 | Oct 30, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 3, 2024 | Dec 3, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 4, 2024 | Dec 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 4, 2024 | Dec 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 4, 2024 | Dec 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2024 | Dec 11, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2024 | Dec 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2024 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $439,000
| Name | Role | License on permit |
|---|---|---|
| Andrew Bruce Morrall Andrew Morrall Architect | Architect | C26696 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026