65 Joost Av
San Francisco permit 202312082229 · West of Twin Peaks
No work to existing bldg. add/construct 2 level deck for multi-residential home.add 2 entry doors,centered on interior hallway,add exterior wall sconce lighting,wiring and switches.
- Filed
- Dec 8, 2023
- Issued
- Oct 8, 2024 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 32 stops across 4 departments
- Comments issued
- 12 times, by Planning, Building Inspection, Public Works, Permit Center
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 8, 2023 | Jan 16, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 16, 2024 | Jun 11, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 16, 2024 | Sep 23, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jun 12, 2024 | Jun 13, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 13, 2024 | Jun 24, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 13, 2024 | Jul 3, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 19, 2024 | Jul 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 19, 2024 | Jul 26, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 19, 2024 | Jul 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 18, 2024 | Sep 19, 2024 | Approved |
Zoning review Planning · CP-ZOC | Sep 18, 2024 | Sep 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 18, 2024 | Sep 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2024 | Oct 8, 2024 | Administrative |
Addendum 1: Final- rear deck engineering
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 9, 2024 | Oct 22, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 17, 2024 | Oct 17, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Oct 18, 2024 | Oct 18, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 22, 2024 | Oct 22, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Oct 30, 2024 | Nov 18, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 14, 2024 | Nov 14, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Nov 18, 2024 | Nov 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 18, 2024 | Nov 21, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Jan 6, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 21, 2024 | Jan 11, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 21, 2024 | Apr 21, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 6, 2025 | Jan 6, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 20, 2025 | Feb 21, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 20, 2025 | Feb 21, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 13, 2025 | Mar 14, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 13, 2025 | Mar 17, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 28, 2025 | Apr 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 28, 2025 | Mar 28, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 21, 2025 | Jul 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $35,000
| Name | Role | License on permit |
|---|---|---|
| Juan Bautista Aleman Hernandez Tangobuilder | Engineer | C86746 |
| Siavash Soroushian Eas Designers | Engineer | C94523 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022