San Francisco permit 202312132404 · Noe Valley

New buildingFull plan reviewIssued
Street view · Jul 2022
Google Street View of 4024 25th St, Jul 2022
Scope of work
As written on the permit application.

To erect a 4-story, 2 residential units, r-3, type vb building.

Timeline
Key dates from the city record.
Filed
Dec 13, 2023
Issued
Aug 21, 2024 (8 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
59 stops across 7 departments
Comments issued
10 times, by Building Inspection, Public Utilities, Public Works, Planning

Main permit

Review stopFinishedResult

Code enforcement

Building Inspection · CES

Dec 13, 2023—

Central Permit Bureau

Building Inspection · CPB

Dec 19, 2023Administrative

Zoning review

Planning · CP-ZOC

Apr 26, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jul 10, 2024Administrative

Building plan review

Building Inspection · BLDG

May 22, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

May 6, 2024Approved

Street use and mapping

Public Works · DPW-BSM

May 1, 2024Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

May 7, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

May 1, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

May 6, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 5, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jun 14, 2024Approved

Zoning review

Planning · CP-ZOC

Jun 18, 2024Approved

Fire prevention review

Fire Department · SFFD

Jun 20, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 25, 2024Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Jun 17, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

Jun 28, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Jul 2, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 2, 2024Approved

Development fee collection

Building Inspection · DFCU

Jul 3, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Aug 21, 2024Administrative

Addendum 1: Shoring, grading and drainage

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Sep 3, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Aug 28, 2024Not Applicable

Electrical pre-screening

Building Inspection · PRE-MECH-E

Aug 29, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Aug 30, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Sep 5, 2024Administrative

Zoning review

Planning · CP-ZOC

Sep 18, 2024Approved

Building plan review

Building Inspection · BLDG

Sep 26, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Sep 6, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 6, 2024Administrative

Public health review

Public Health · HEALTH

Sep 5, 2024Not Applicable

Permit Processing Center

Building Inspection · PPC

Mar 5, 2025Administrative

Development fee collection

Building Inspection · DFCU

Sep 27, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Mar 12, 2025Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Nov 14, 2024Approved

Addendum 2: Foundation, superstruc, arch,mep,t24

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Sep 3, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Aug 29, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Aug 30, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Aug 30, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Sep 5, 2024Administrative

Zoning review

Planning · CP-ZOC

Sep 18, 2024Approved

Building plan review

Building Inspection · BLDG

Sep 27, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 18, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 11, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Sep 11, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 6, 2024Approved

Permit Processing Center

Building Inspection · PPC

Dec 3, 2024Administrative

Urban forestry

Public Works · DPW-BUF

Sep 11, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 18, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 4, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Nov 5, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 12, 2024Approved

Urban forestry

Public Works · DPW-BUF

Nov 12, 2024Approved

Zoning review

Planning · CP-ZOC

Nov 12, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 13, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Nov 13, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 14, 2024Approved

Zoning review

Planning · CP-ZOC

Nov 19, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Mar 10, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Issued
Estimated cost
$1,950,677
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
John Patrick Maniscalco

John Maniscalco Architecture

ArchitectC25148
David M Strandberg

Strandberg Engineering

Engineer62993
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202312132404 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record