188 The Embarcadero
San Francisco permit 202312142507 · Financial District/South Beach
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
3/f: revision to pa# 202212198622, to construct a hallway at stair #2 and the addition of a coffee and bevi machine and fridge with millwork modifications.
- Filed
- Dec 14, 2023
- Issued
- Jan 3, 2024 (within 1 month of filing)
- Completed
- Apr 17, 2024 (3 months after issuance)
- Review stops
- 6 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 14, 2023 | Dec 14, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 14, 2023 | Dec 14, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 14, 2023 | Dec 14, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 21, 2023 | Dec 21, 2023 | Approved |
Public health review Public Health · HEALTH | Dec 21, 2023 | Dec 22, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 3, 2024 | Jan 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Donna Kim Cook Brereton | Architect | C34846 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026