San Francisco permit 202312152601 · Potrero Hill

Commercial or tenant improvementFull plan reviewIssued
Street view · Sep 2026
Google Street View of 2146 03rd St, Sep 2026
Scope of work
As written on the permit application.

Ti interior removation of all 3 levels; accessble entry upgrade to commercial space, interior renovation of dwelling unit. sprinkler under separate permit

Timeline
Key dates from the city record.
Filed
Dec 15, 2023
Issued
Aug 5, 2024 (8 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
29 stops across 6 departments
Comments issued
9 times, by Building Inspection, Public Utilities
Review stopFinishedResult

Plumbing inspector

Building Inspection · PID-INSP

Nov 30, 2023Approved

Intake

Building Inspection · INTAKE

Dec 15, 2023Administrative

Zoning review

Planning · CP-ZOC

Dec 15, 2023Approved

Permit Center

Permit Center · PERMIT-CTR

Dec 15, 2023—

Central Permit Bureau

Building Inspection · CPB

Dec 26, 2023Administrative

Building plan review

Building Inspection · BLDG

Feb 7, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 22, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Apr 8, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 16, 2024Issued Comments

Central Permit Bureau

Building Inspection · CPB

May 29, 2024Administrative

Building plan review

Building Inspection · BLDG

Jun 5, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 17, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

May 30, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jun 17, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 10, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 27, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 4, 2024Approved

Zoning review

Planning · CP-ZOC

May 29, 2024Approved

Zoning review

Planning · CP-ZOC

May 29, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jul 30, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jun 19, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 20, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 26, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 8, 2024Approved

Building plan review

Building Inspection · BLDG

Jul 9, 2024Approved

Zoning review

Planning · CP-ZOC

Jul 25, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 19, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jul 19, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Aug 5, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$940,796
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Maxine Skaggs KennedyArchitectC33712
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202312152601 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record