3928 Geary Bl
San Francisco permit 202312152602 · Inner Richmond
Barrier removal - new accessible unisex toilet room @ ground floor level. interior work only
- Filed
- Dec 15, 2023
- Issued
- Dec 15, 2023 (within 1 month of filing)
- Completed
- Apr 26, 2024 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2023 were typically issued within 1 month (median of 4,704 issued permits).
- Review stops
- 6 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Dec 15, 2023 | Dec 15, 2023 | Administrative |
Intake Building Inspection · INTAKE | Dec 15, 2023 | Dec 15, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 15, 2023 | Dec 15, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 15, 2023 | Dec 15, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2023 | Dec 15, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 15, 2023 | Dec 15, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $20,000
| Name | Role | License on permit |
|---|---|---|
| Patric Darren Mcmurtrie | Architect | C-29072 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026