3824 21st St
San Francisco permit 202312192726 · Castro/Upper Market
Renovation of (e) sfh includes reconfiguration of upper level, adding windows to rear exterior of bldg, and addition of a rear upper level deck to rear of home.
- Filed
- Dec 19, 2023
- Issued
- Dec 2, 2024 (11 months after filing)
- Completed
- Aug 28, 2026 (21 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 35 stops across 6 departments
- Comments issued
- 10 times, by Planning, Building Inspection, Permit Center, Fire Department
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 19, 2023 | Dec 29, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 29, 2023 | Apr 15, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 29, 2023 | Oct 25, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 7, 2024 | May 20, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 11, 2024 | Jun 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 14, 2024 | Jun 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 14, 2024 | Jul 2, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 14, 2024 | Jun 25, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 28, 2024 | Jul 22, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 17, 2024 | Oct 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 22, 2024 | Oct 25, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 25, 2024 | Dec 2, 2024 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 9, 2025 | Jan 21, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 24, 2025 | Feb 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 10, 2025 | Feb 12, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 12, 2025 | Feb 13, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 12, 2025 | Mar 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2025 | Apr 2, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 12, 2025 | Feb 13, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2025 | Feb 18, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2025 | Feb 20, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 12, 2025 | Jun 5, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 28, 2025 | Mar 31, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 11, 2025 | Apr 22, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 11, 2025 | Apr 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 11, 2025 | Apr 11, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 11, 2025 | Apr 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 11, 2025 | May 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 11, 2025 | Apr 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 15, 2025 | May 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 27, 2025 | May 27, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 28, 2025 | Jun 2, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2025 | May 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2025 | Jun 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 5, 2025 | Jun 13, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Jeffrey Scott Mcgrew Jeffrey Mcgrew | Architect | C32623 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025