55 Dolores St
San Francisco permit 202312212977 · Mission
New roof deck(659 sq ft)pethouse extension (55 sq ft) structrual work as indicated on the plans.
- Filed
- Dec 21, 2023
- Issued
- May 23, 2025 (17 months after filing)
- Completed
- Jun 26, 2026 (13 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 13 stops across 3 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 21, 2023 | Feb 5, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 5, 2024 | Aug 14, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 5, 2024 | Dec 12, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 14, 2024 | Aug 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 14, 2024 | Jul 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 14, 2024 | Aug 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 27, 2024 | Sep 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 9, 2024 | Oct 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 11, 2024 | Oct 18, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2024 | Oct 21, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 11, 2024 | Oct 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2024 | May 23, 2025 | Administrative |
Apartment and hotel inspection Building Inspection · HIS | May 22, 2025 | May 22, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $82,000
| Name | Role | License on permit |
|---|---|---|
| Sean Thomas Condry Stc Design & Engineering | Engineer | C60860 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025