15 Carmel St
San Francisco permit 202312212983 · Inner Sunset
Horizontal and vertical expansion of (e) sfd. int remodel throughout. automatic sprinkler throughout building under separate permit.
- Filed
- Dec 21, 2023
- Issued
- Apr 8, 2025 (16 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 31 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 21, 2023 | Jan 2, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 2, 2024 | Jun 28, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 2, 2024 | Mar 28, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 28, 2024 | Aug 9, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 28, 2024 | Jul 23, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 28, 2024 | Aug 14, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 28, 2024 | Jul 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2024 | Jul 23, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 5, 2024 | Jul 8, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Nov 4, 2024 | Nov 13, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 4, 2024 | Nov 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 14, 2024 | Nov 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 2, 2024 | Dec 16, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 2, 2024 | Dec 2, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 2, 2024 | Dec 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 2, 2024 | Dec 6, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Dec 2, 2024 | Dec 3, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 2, 2024 | Mar 20, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 2, 2024 | Dec 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 6, 2025 | Jan 14, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Jan 9, 2025 | Jan 9, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 16, 2025 | Feb 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 18, 2025 | Feb 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2025 | Mar 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 20, 2025 | Mar 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 20, 2025 | Mar 20, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Mar 24, 2025 | Mar 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 24, 2025 | Mar 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2025 | Mar 25, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Mar 26, 2025 | Mar 27, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 28, 2025 | Apr 8, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,510,916
| Name | Role | License on permit |
|---|---|---|
| Tom Amedeo Mcelroy Mcelroy Architecture | Architect | C30930 |
| Donald David Double D Enginneering, Inc | Engineer | 3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2022