Scope of work
As written on the permit application.

3-story rear yard additional. new dormer & interior remodel.

Timeline
Key dates from the city record.
Filed
Dec 22, 2023
Issued
Feb 24, 2025 (14 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
47 stops across 6 departments
Comments issued
16 times, by Planning, Building Inspection, Public Works, Public Utilities, Fire Department

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 27, 2023Administrative

Zoning review

Planning · CP-ZOC

Mar 26, 2024Issued Comments

Zoning review

Planning · CP-ZOC

May 30, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 11, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jun 13, 2024Approved-Stipulated

Building plan review

Building Inspection · BLDG

Jun 13, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

Jun 29, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jun 20, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

Jul 17, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 22, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jul 24, 2024Approved

Building plan review

Building Inspection · BLDG

Aug 15, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Aug 16, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Aug 20, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 20, 2024Approved

Zoning review

Planning · CP-ZOC

Sep 12, 2024Approved

Fire prevention review

Fire Department · SFFD

Sep 24, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 27, 2024Approved

Urban forestry

Public Works · DPW-BUF

Dec 5, 2024Approved-Stipulated

Development fee collection

Building Inspection · DFCU

Jan 29, 2025Administrative

Permit Processing Center

Building Inspection · PPC

Feb 7, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Feb 24, 2025Administrative

Addendum 1: Final addenda

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jun 10, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jun 12, 2025Administrative

Zoning review

Planning · CP-ZOC

Jun 12, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 8, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 1, 2025Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

Jul 19, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 13, 2025Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Jun 24, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Aug 6, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 13, 2025Approved

Permit Processing Center

Building Inspection · PPC

Nov 10, 2025Administrative

Zoning review

Planning · CP-ZOC

Nov 10, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 22, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 3, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 7, 2025Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Oct 6, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Oct 14, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Oct 3, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 10, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 31, 2025Approved

Fire prevention review

Fire Department · SFFD

Oct 30, 2025Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Oct 30, 2025Approved

Urban forestry

Public Works · DPW-BUF

Nov 7, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 29, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Nov 14, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$656,748
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Andre Joel Rothblatt

Rothblatt Architecture

ArchitectC-22561
Donald David

Double D Engineering

EngineerS3928
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202312223057 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record