306 Ortega St
San Francisco permit 202312263096 · Inner Sunset
Interior renovation to an existing 2-story single-family dwelling. infill existing lightwell with new interior staircase. new master suite behind garage. no change to existing use and height.
| Fact | Before | After |
|---|---|---|
| Use | 1 family dwelling | No change |
| Units | 1 | No change |
| Stories | 2 | No change |
- Filed
- Dec 26, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 17 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 26, 2023 | Jan 4, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 4, 2024 | Mar 6, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 4, 2024 | Jul 10, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 12, 2024 | May 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 12, 2024 | Apr 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 12, 2024 | Mar 13, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 12, 2024 | Mar 27, 2024 | Approved |
Mechanical plan review quality control Building Inspection · MECH-QC | Apr 19, 2024 | Apr 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 13, 2024 | May 13, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 13, 2024 | May 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2024 | May 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 30, 2024 | May 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 26, 2024 | Jun 26, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 28, 2024 | Jul 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 28, 2024 | Jul 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2024 | Jul 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 10, 2024 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $158,600
- Cost after review
- $170,0007% higher
| Name | Role | License on permit |
|---|---|---|
| Wing Kin Lee Wing Lee Architects | Architect | C28929 |
| Lou Xiao Lx Engineering | Engineer | S5130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2008