CheckMyDesigner

776 14th St

San Francisco permit 202312293264 · Castro/Upper Market

ADUFull plan reviewComplete
Street view · Sep 2026
Google Street View of 776 14th St, Sep 2026
Scope of work
As written on the permit application.

Legalize (e) ground floor udu to provide 1 adu studio- unit 776a will be added per calfiornia government code section 65852.2. add new fire department access hallway at ground floor from open air entrance at front to rear yard for fire dept. ladder access.

Timeline
Key dates from the city record.
Filed
Dec 29, 2023
Issued
Aug 6, 2024 (7 months after filing)
Completed
Sep 9, 2025 (13 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
28 stops across 5 departments
Comments issued
7 times, by Planning, Building Inspection, Public Works
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 16, 2024Administrative

Zoning review

Planning · CP-ZOC

Mar 27, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Jul 26, 2024Administrative

Building plan review

Building Inspection · BLDG

Apr 17, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 22, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Apr 2, 2024Approved

Urban forestry

Public Works · DPW-BUF

Apr 2, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 1, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 5, 2024Approved

Building plan review

Building Inspection · BLDG

May 29, 2024Approved

Zoning review

Planning · CP-ZOC

May 22, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Jun 12, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 21, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

Jun 18, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jun 13, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 12, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 2, 2024Approved

Fire prevention review

Fire Department · SFFD

Jun 12, 2024Approved

Urban forestry

Public Works · DPW-BUF

Jun 21, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 24, 2024Approved

Zoning review

Planning · CP-ZOC

Jun 27, 2024Administrative

Zoning review

Planning · CP-ZOC

Jun 27, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 27, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 28, 2024Approved

Urban forestry

Public Works · DPW-BUF

Jul 17, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 1, 2024Approved

Development fee collection

Building Inspection · DFCU

Jul 18, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Aug 6, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$144,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Kyle Tamar Brunel

Pencil Box Architects

ArchitectC35905
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202312293264 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record