CheckMyDesigner

365 Toni Stone Cg

San Francisco permit 202312293282 · Mission Bay

Revision or supplementFull plan reviewApproved

This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.

Street view · Sep 2026
Google Street View of 365 Toni Stone Cg, Sep 2026
Scope of work
As written on the permit application.

Proj-23-0563: prority process - mayor dir# 17-02. mou proj port of sf: revision to 2019-1007-3784 s3 / arch + mep addendum s3. revision to port application # b-2022-0127 & dbi pa #201910073784 s3. aka mission rock-bldg f.

Timeline
Key dates from the city record.
Filed
Dec 29, 2023
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
18 stops across 4 departments
Comments issued
3 times, by Building Inspection, Fire Department
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 9, 2024Administrative

Building plan review

Building Inspection · BLDG

Jan 31, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 2, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jan 18, 2024Approved

Fire Department

SFFD-PRT

Feb 28, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jan 10, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Jan 10, 2024Approved

Permit Processing Center

Building Inspection · PPC

Mar 26, 2024Administrative

Fire Department

SFFD-PRT

Mar 20, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 21, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 22, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Mar 25, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Mar 22, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Mar 25, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 25, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 25, 2024Approved

Fire Department

SFFD-PRT

Mar 25, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Apr 10, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Approved
Estimated cost
$896,904
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jeanne K GangArchitectC34329
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202312293282 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record