Proj-23-0563: prority process - mayor dir# 17-02. mou proj port of sf: revision to 2019-1007-3784 s3 / arch + mep addendum s3. revision to port application # b-2022-0127 & dbi pa #201910073784 s3. aka mission rock-bldg f.
- Filed
- Dec 29, 2023
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 18 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 29, 2023 | Jan 9, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 9, 2024 | Jan 31, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2024 | Feb 2, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 9, 2024 | Jan 18, 2024 | Approved |
Fire Department SFFD-PRT | Jan 9, 2024 | Feb 28, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2024 | Jan 10, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2024 | Jan 10, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 9, 2024 | Mar 26, 2024 | Administrative |
Fire Department SFFD-PRT | Mar 20, 2024 | Mar 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 21, 2024 | Mar 21, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 22, 2024 | Mar 22, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 22, 2024 | Mar 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 22, 2024 | Mar 22, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 22, 2024 | Mar 25, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 25, 2024 | Mar 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 25, 2024 | Mar 25, 2024 | Approved |
Fire Department SFFD-PRT | Mar 25, 2024 | Mar 25, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 26, 2024 | Apr 10, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $896,904
| Name | Role | License on permit |
|---|---|---|
| Jeanne K Gang | Architect | C34329 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026