25 Whitney St
San Francisco permit 202312293293 · Glen Park
New 1-story rear yard addition w/ roof deck and exterior stair, replace existing interior communication stair between 1st and 2nd floors, new full bathroom @ 1st floor, relocation of laundry @ 1st floor, new fire separation between garage & 1st and 2nd floor living spaces, new roof top pv solar
- Filed
- Dec 29, 2023
- Issued
- Jul 3, 2024 (6 months after filing)
- Completed
- Sep 5, 2025 (14 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 29, 2023 | Jan 2, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 2, 2024 | Feb 29, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 2, 2024 | Jul 1, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 29, 2024 | Apr 26, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 29, 2024 | Mar 19, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 29, 2024 | Mar 29, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 29, 2024 | Mar 13, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 29, 2024 | Mar 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 8, 2024 | May 16, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2024 | May 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 8, 2024 | May 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 8, 2024 | May 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 8, 2024 | May 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 8, 2024 | May 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 30, 2024 | Jun 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 30, 2024 | Jun 3, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | May 30, 2024 | May 31, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2024 | Jun 13, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 30, 2024 | Jul 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 30, 2024 | Jun 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 3, 2024 | Jun 3, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 1, 2024 | Jul 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $239,306
| Name | Role | License on permit |
|---|---|---|
| Christian J Dauer Chr Dauer Architect | Architect | C28302 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020