CheckMyDesigner

25 Whitney St

San Francisco permit 202312293293 · Glen Park

AdditionFull plan reviewComplete
Street view · Dec 2020
Google Street View of 25 Whitney St, Dec 2020
Scope of work
As written on the permit application.

New 1-story rear yard addition w/ roof deck and exterior stair, replace existing interior communication stair between 1st and 2nd floors, new full bathroom @ 1st floor, relocation of laundry @ 1st floor, new fire separation between garage & 1st and 2nd floor living spaces, new roof top pv solar

Timeline
Key dates from the city record.
Filed
Dec 29, 2023
Issued
Jul 3, 2024 (6 months after filing)
Completed
Sep 5, 2025 (14 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2023 typically took 9 months to be issued (median of 574 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 5 departments
Comments issued
7 times, by Building Inspection, Fire Department, Public Works, Public Utilities
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 2, 2024Administrative

Zoning review

Planning · CP-ZOC

Feb 29, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jul 1, 2024Administrative

Building plan review

Building Inspection · BLDG

Apr 26, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 19, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 29, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 13, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 5, 2024Approved

Building plan review

Building Inspection · BLDG

May 16, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 29, 2024Approved

Fire prevention review

Fire Department · SFFD

May 9, 2024Approved

Street use and mapping

Public Works · DPW-BSM

May 9, 2024Approved

Zoning review

Planning · CP-ZOC

May 20, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 13, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jun 4, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 3, 2024Issued Comments

Zoning review

Planning · CP-ZOC

May 31, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 13, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 1, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 28, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 3, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jul 3, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$239,306
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Christian J Dauer

Chr Dauer Architect

ArchitectC28302
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202312293293 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record