1080 Francisco St
San Francisco permit 202401083557 · Russian Hill
Voluntary seismic upgrade at the garage level.
- Filed
- Jan 8, 2024
- Issued
- Jul 17, 2024 (6 months after filing)
- Completed
- Sep 18, 2024 (2 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 16 stops across 4 departments
- Comments issued
- 3 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 2, 2024 | Jan 23, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 8, 2024 | Jan 8, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Jan 23, 2024 | Jan 23, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Feb 6, 2024 | Feb 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 13, 2024 | Feb 23, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 23, 2024 | May 1, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 23, 2024 | Mar 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2024 | Mar 15, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 23, 2024 | Jul 16, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 6, 2024 | May 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 28, 2024 | Jun 28, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 1, 2024 | Jul 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2024 | Jul 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 11, 2024 | Jul 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 11, 2024 | Jul 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 16, 2024 | Jul 17, 2024 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $119,000
| Name | Role | License on permit |
|---|---|---|
| Behruz Vahdani-Sanavi Matrix Seismic Corp. | Engineer | C-35605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026