750 Golden Gate Av
San Francisco permit 202401083599 · Western Addition
100% affordable housing. erect 8 story type 1a, residential 75 units, parking, office assembly (r-2,s-1,s-2,b,a-3). mayor ed 13-01
- Filed
- Mar 8, 2024
- Issued
- Jul 12, 2024 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 188 stops across 7 departments
- Comments issued
- 46 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 8, 2024 | Jan 19, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jan 9, 2024 | Jan 9, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 9, 2024 | Jan 9, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Jan 10, 2024 | Mar 8, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jan 18, 2024 | Jan 29, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 24, 2024 | Jan 24, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Jan 25, 2024 | Jan 25, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 1, 2024 | Mar 6, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 8, 2024 | Mar 11, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Mar 8, 2024 | Apr 18, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 8, 2024 | Apr 9, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 8, 2024 | Mar 27, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 8, 2024 | Mar 18, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Mar 8, 2024 | May 2, 2024 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Mar 8, 2024 | Jul 3, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Apr 9, 2024 | May 3, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2024 | Apr 10, 2024 | Approved |
Public health review Public Health · HEALTH | May 2, 2024 | May 2, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | May 13, 2024 | May 13, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 13, 2024 | May 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 14, 2024 | May 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 6, 2024 | Jun 6, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 11, 2024 | Jun 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 21, 2024 | Jun 21, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 26, 2024 | Jun 26, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jun 27, 2024 | Jun 27, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Jun 28, 2024 | Jul 2, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2024 | Jun 28, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 3, 2024 | Jul 12, 2024 | Administrative |
Addendum 1: Dept. of public health - maher ordinance
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 29, 2024 | Aug 2, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Aug 1, 2024 | Aug 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 5, 2024 | Aug 5, 2024 | Administrative |
Public health review Public Health · HEALTH | Aug 5, 2024 | Aug 6, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 5, 2024 | Nov 5, 2024 | Administrative |
Public health review Public Health · HEALTH | Nov 1, 2024 | Nov 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 5, 2024 | Dec 6, 2024 | Administrative |
Addendum 2: Shoring, excavation & ground improvement
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 18, 2024 | Jul 25, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jul 24, 2024 | Jul 24, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 24, 2024 | Jul 24, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 25, 2024 | Jul 25, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Jul 25, 2024 | Jul 25, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 25, 2024 | Aug 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2024 | Jul 29, 2024 | Approved |
Public health review Public Health · HEALTH | Jul 25, 2024 | Aug 9, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 25, 2024 | Nov 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 1, 2024 | Nov 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 1, 2024 | Nov 1, 2024 | Approved |
Public health review Public Health · HEALTH | Nov 1, 2024 | Nov 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 6, 2024 | Dec 6, 2024 | Administrative |
Addendum 3: Foundation + superstruture
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 18, 2024 | Jul 25, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jul 24, 2024 | Jul 24, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 24, 2024 | Jul 24, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 25, 2024 | Jul 25, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Jul 25, 2024 | Jul 25, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 25, 2024 | Aug 13, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2024 | Jul 29, 2024 | Approved |
Public health review Public Health · HEALTH | Jul 25, 2024 | Aug 13, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 25, 2024 | Nov 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 27, 2024 | Oct 4, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 15, 2024 | Oct 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 30, 2024 | Nov 1, 2024 | Approved |
Public health review Public Health · HEALTH | Oct 30, 2024 | Nov 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 5, 2024 | Dec 6, 2024 | Administrative |
Addendum 4: Architectural & mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 23, 2024 | Sep 9, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 30, 2024 | Aug 30, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 3, 2024 | Sep 3, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 4, 2024 | Sep 4, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 9, 2024 | Sep 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 9, 2024 | Sep 9, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 9, 2024 | Oct 23, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2024 | Sep 27, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Sep 9, 2024 | Sep 23, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 9, 2024 | Sep 25, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 9, 2024 | Sep 11, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 9, 2024 | Sep 11, 2024 | Approved |
Zoning review Planning · CP-ZOC | Sep 9, 2024 | Sep 11, 2024 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Sep 9, 2024 | May 20, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Sep 23, 2024 | Sep 23, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 26, 2024 | Dec 23, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 26, 2024 | Dec 2, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 27, 2024 | Nov 27, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 2, 2024 | Dec 5, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 6, 2024 | Dec 6, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 6, 2024 | Dec 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 6, 2024 | Feb 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 6, 2024 | Dec 11, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 6, 2024 | Dec 9, 2024 | Not Applicable |
Electrical plan review Building Inspection · MECH-E | Feb 11, 2025 | Feb 18, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 17, 2025 | Feb 27, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 18, 2025 | Feb 18, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 18, 2025 | May 2, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 18, 2025 | Apr 18, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 24, 2025 | Apr 24, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 13, 2025 | May 16, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | May 14, 2025 | May 14, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2025 | May 19, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 16, 2025 | May 19, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 16, 2025 | May 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 16, 2025 | May 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 20, 2025 | May 29, 2025 | Administrative |
Addendum 5: Landscape & stormwater pid review
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 7, 2025 | May 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 27, 2025 | May 27, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 27, 2025 | Jun 16, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 27, 2025 | Jun 17, 2025 | Approved |
Plumbing plan check Building Inspection · PID-PC | May 27, 2025 | Jul 16, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 27, 2025 | Dec 12, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Oct 30, 2025 | Nov 5, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 30, 2025 | Nov 7, 2025 | Approved |
Plumbing plan check Building Inspection · PID-PC | Oct 30, 2025 | Nov 7, 2025 | Issued Comments |
Plumbing plan check Building Inspection · PID-PC | Oct 30, 2025 | Nov 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2025 | Jan 12, 2026 | Administrative |
Addendum 6: Fire sprinkler system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 25, 2025 | Mar 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 10, 2025 | Mar 10, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 10, 2025 | Mar 25, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 10, 2025 | Aug 18, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Jun 5, 2025 | Jun 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 5, 2025 | Aug 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 18, 2025 | Aug 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 18, 2025 | Aug 19, 2025 | Administrative |
Addendum 7: Fire alarm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 21, 2025 | Nov 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 12, 2025 | Nov 12, 2025 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Nov 12, 2025 | Nov 26, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 12, 2025 | Jul 24, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Apr 22, 2026 | May 13, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jun 23, 2026 | Jul 10, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jul 15, 2026 | Jul 15, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 24, 2026 | Aug 4, 2026 | Administrative |
Addendum 8: Metal stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 20, 2025 | Sep 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2025 | Sep 4, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 4, 2025 | Sep 18, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 4, 2025 | Sep 18, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Sep 4, 2025 | Sep 29, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 4, 2025 | Jan 14, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 6, 2026 | Jan 6, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 8, 2026 | Jan 9, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 9, 2026 | Jan 9, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jan 9, 2026 | Jan 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 14, 2026 | Jan 15, 2026 | Administrative |
Addendum 9: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 27, 2026 | Jan 27, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 27, 2026 | Feb 19, 2026 | Not Applicable |
Fire Department housing review Fire Department · SFFD-HQ | Jan 27, 2026 | Feb 2, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 27, 2026 | Feb 19, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 19, 2026 | Feb 26, 2026 | Administrative |
Addendum 10: Exterior building maintenance system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 27, 2026 | Jan 27, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jan 27, 2026 | Feb 25, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jan 27, 2026 | Jan 28, 2026 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Jan 27, 2026 | Mar 17, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Mar 16, 2026 | Mar 16, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Mar 16, 2026 | Mar 17, 2026 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Mar 17, 2026 | Mar 18, 2026 | Administrative |
Addendum 11: Solar pv
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 29, 2026 | Jan 29, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 29, 2026 | Feb 27, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 29, 2026 | Feb 27, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 29, 2026 | Feb 11, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jan 29, 2026 | Feb 2, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 29, 2026 | Jun 29, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 13, 2026 | Apr 13, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 13, 2026 | Apr 13, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 17, 2026 | Apr 17, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Apr 17, 2026 | Apr 22, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | May 4, 2026 | Jun 25, 2026 | Approved-Stipulated |
Electrical plan review Building Inspection · MECH-E | May 11, 2026 | May 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 25, 2026 | Jun 26, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 25, 2026 | Jun 26, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 29, 2026 | Jul 8, 2026 | Administrative |
Addendum 12: Tower crane
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 27, 2025 | Feb 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 4, 2025 | Feb 4, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Feb 4, 2025 | Feb 20, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 4, 2025 | Feb 6, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 4, 2025 | Apr 9, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Apr 2, 2025 | Apr 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 8, 2025 | Apr 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 9, 2025 | Apr 10, 2025 | Administrative |
Addendum 13: Rev1 to addendum 2-shoring, excavate & gr improv
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 14, 2025 | Mar 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 17, 2025 | Mar 31, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 31, 2025 | Apr 25, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 31, 2025 | Apr 3, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Mar 31, 2025 | Apr 1, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Mar 31, 2025 | Apr 25, 2025 | Administrative |
Public Health HEALTH-MH | Apr 1, 2025 | Apr 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2025 | Apr 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 25, 2025 | Apr 30, 2025 | Administrative |
Addendum 14: Emergency evac signage.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 15, 2026 | Jul 6, 2026 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Jun 22, 2026 | Jul 9, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jul 7, 2026 | Jul 9, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jul 10, 2026 | Jul 15, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 10, 2026 | Jul 15, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 15, 2026 | Jul 16, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $37,100,000
| Name | Role | License on permit |
|---|---|---|
| Caroline Joy Souza David Baker Architects | Architect | C-35830 |
| Jason J. Ling Urban Design Consulting Eng | Engineer | C60493 |
| Kai Shing Chu Spi Consulting Engineers, Inc. | Engineer | C84827 |
| David Joseph Rossi Kpff | Engineer | 4127 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025