This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to approved permit# 201808167612: including the lighting plan, kitchen and bar equipment layout, relocate water heater, add funnel drain at backbar and updated mechanical plans, remove electrical water heater.
- Filed
- Jan 12, 2024
- Issued
- Mar 4, 2024 (2 months after filing)
- Completed
- Feb 28, 2025 (12 months after issuance)
- Review stops
- 14 stops across 5 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 12, 2024 | Jan 12, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 12, 2024 | Jan 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 12, 2024 | Jan 12, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 12, 2024 | Jan 12, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | Feb 5, 2024 | Feb 5, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 5, 2024 | Feb 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 5, 2024 | Feb 5, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 5, 2024 | Feb 5, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | Feb 14, 2024 | Feb 14, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Feb 14, 2024 | Feb 14, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 14, 2024 | Feb 14, 2024 | Approved-Stipulated |
Public health review Public Health · HEALTH | Feb 14, 2024 | Feb 14, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Feb 21, 2024 | Feb 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 4, 2024 | Mar 4, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Matthew H Hollis | Architect | C-28252 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025