651 Brannan St
San Francisco permit 202401184198 · Mission Bay
Electrical work, replacement of roof-mounted generator, replacement of ats and addition of mts in 3/f electrical room, and addtiion of portable genrator connection cabinet in basement.
- Filed
- Jan 18, 2024
- Issued
- Apr 25, 2024 (3 months after filing)
- Completed
- Not completed yet
- Review stops
- 20 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Permit Center
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 18, 2024 | Jan 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 18, 2024 | Jan 18, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Jan 18, 2024 | Jan 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 22, 2024 | Jan 22, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jan 23, 2024 | Feb 1, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 24, 2024 | Jan 24, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Feb 1, 2024 | Feb 1, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Feb 8, 2024 | Feb 14, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 12, 2024 | Feb 12, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 12, 2024 | Feb 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 15, 2024 | Feb 16, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Feb 16, 2024 | Feb 23, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 16, 2024 | Mar 20, 2024 | Approved |
Public health review Public Health · HEALTH | Feb 16, 2024 | Feb 20, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 16, 2024 | Apr 19, 2024 | — |
Electrical plan review Building Inspection · MECH-E | Apr 1, 2024 | Apr 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 8, 2024 | Apr 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 8, 2024 | Apr 10, 2024 | Approved |
Public health review Public Health · HEALTH | Apr 8, 2024 | Apr 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 19, 2024 | Apr 25, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $575,000
| Name | Role | License on permit |
|---|---|---|
| Carl Milsum Carl Milsum | Engineer | S6190 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026