4248 23rd St
San Francisco permit 202401184206 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to permit 202302021280. revise drawings to remove reference to fire alarms/domes. remove note indicating fire permits per bldg inspector request and fire requirement not required by code. existing 2-hr assembly between occupancies. not required by code
- Filed
- Jan 18, 2024
- Issued
- Jan 19, 2024 (within 1 month of filing)
- Completed
- Jan 19, 2024 (within 1 month of issuance)
- Review stops
- 5 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 18, 2024 | Jan 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 18, 2024 | Jan 18, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 18, 2024 | Jan 18, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 18, 2024 | Jan 18, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 19, 2024 | Jan 19, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Brittney P Epperson | Architect | C35300 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026