1288 Howard St #4
San Francisco permit 202401194296 · South of Market
Space 4: convert vacant commercial space to a full service restaurant. mep deferred.
- Filed
- Jan 19, 2024
- Issued
- Aug 2, 2024 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 28 stops across 7 departments
- Comments issued
- 3 times, by Building Inspection, Public Utilities, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 19, 2024 | Jan 19, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 19, 2024 | Jan 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 19, 2024 | Jan 19, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 22, 2024 | Jan 22, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 22, 2024 | Jan 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 22, 2024 | Jan 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 22, 2024 | Jan 22, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2024 | Jan 24, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 4, 2024 | Mar 12, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 6, 2024 | Mar 6, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 6, 2024 | Mar 6, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Mar 11, 2024 | Mar 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 12, 2024 | Mar 18, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 19, 2024 | Mar 21, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2024 | Mar 26, 2024 | Approved |
Public health review Public Health · HEALTH | Mar 19, 2024 | Apr 3, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 19, 2024 | Jul 23, 2024 | Administrative |
Public health review Public Health · HEALTH | Apr 3, 2024 | Apr 3, 2024 | Administrative |
Public health review Public Health · HEALTH | Jul 12, 2024 | Jul 18, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 12, 2024 | Jul 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 12, 2024 | Jul 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2024 | Jul 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 12, 2024 | Jul 23, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 12, 2024 | Jul 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 12, 2024 | Jul 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 19, 2024 | Jul 22, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | Jul 22, 2024 | Jul 22, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2024 | Aug 2, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Janet Coral Campbell Campbell & Associates | Architect | C18808 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2020