259 07th Av
San Francisco permit 202401244517 · Inner Richmond
To establish state adu on ground floor and interior alterations/facade modifications, with electrical, plumbing and structural work. (2 residential units + adu)
- Filed
- Jan 24, 2024
- Issued
- Aug 19, 2024 (7 months after filing)
- Completed
- Mar 27, 2026 (19 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 27 stops across 6 departments
- Comments issued
- 9 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 21, 2024 | Jan 29, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 24, 2024 | Jan 24, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jan 25, 2024 | Jan 25, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Feb 23, 2024 | Mar 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 6, 2024 | Mar 26, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 26, 2024 | Apr 1, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 26, 2024 | Apr 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 26, 2024 | Apr 9, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 26, 2024 | Mar 28, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 26, 2024 | Apr 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 26, 2024 | Apr 4, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 26, 2024 | Aug 9, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Apr 1, 2024 | Apr 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 15, 2024 | Apr 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 17, 2024 | Apr 17, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 18, 2024 | Jun 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 7, 2024 | Jun 10, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 17, 2024 | Jun 17, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2024 | Jun 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 20, 2024 | Jun 20, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 21, 2024 | Jun 25, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 2, 2024 | Jul 2, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 2, 2024 | Jul 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 11, 2024 | Jul 11, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 9, 2024 | Aug 9, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Aug 9, 2024 | Aug 9, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 9, 2024 | Aug 19, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $274,000
| Name | Role | License on permit |
|---|---|---|
| Howard E Blecher Blecher Bldg & Urban Design | Architect | C-36464 |
| Nilgun Asci Wolpe N. Y Engineering | Engineer | 68482 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025