80 A Entrada Ct
San Francisco permit 202401264778 · West of Twin Peaks
(unit a) new adu on ground fl (972 sqft), per ca gov code sec 65852.2. add 2 bedrooms, 2 bathrooms, living room & kitchen on (e) ground fl. install plywood wall reinforcement for voluntary ground fl structural strengthening. partial new foundation, reinforce & underpinning (e) footing.
- Filed
- Jan 26, 2024
- Issued
- Jul 8, 2025 (17 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 38 stops across 6 departments
- Comments issued
- 11 times, by Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 25, 2024 | Feb 5, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 29, 2024 | Jan 29, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Feb 5, 2024 | Feb 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 6, 2024 | Feb 6, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 6, 2024 | Mar 8, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 6, 2024 | Mar 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 6, 2024 | Mar 4, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 6, 2024 | Feb 7, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 6, 2024 | Mar 26, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 6, 2024 | Feb 7, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 6, 2024 | Jun 2, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Mar 1, 2024 | Mar 21, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 19, 2024 | Nov 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 19, 2024 | Nov 22, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 19, 2024 | Dec 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 19, 2024 | Dec 3, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 19, 2024 | Dec 9, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 19, 2024 | Nov 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 19, 2024 | Nov 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 27, 2024 | Nov 27, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 28, 2025 | Jan 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 28, 2025 | Jan 28, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 28, 2025 | Feb 10, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 28, 2025 | Feb 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 28, 2025 | Feb 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 28, 2025 | Jan 29, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2025 | Jan 30, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 28, 2025 | May 7, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 30, 2025 | Apr 30, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 5, 2025 | May 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2025 | May 6, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 6, 2025 | May 9, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 12, 2025 | May 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 12, 2025 | May 12, 2025 | Approved |
Development fee collection Building Inspection · DFCU | May 15, 2025 | May 15, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | May 30, 2025 | Jun 2, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jun 2, 2025 | Jul 8, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2025 | Jul 8, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $264,365
| Name | Role | License on permit |
|---|---|---|
| Hawk Lee Hawk N Lee Company | Engineer | C28526 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022