1 Warriors Wy
San Francisco permit 202401294827 · Mission Bay
South tower level 2 and 3, space 11: work includes concrete topping slab at level 2, infill slab opening and new concrete slab on level 3, new steel stair frame, and improvements as shown on plans.
- Filed
- Jan 29, 2024
- Issued
- May 22, 2024 (4 months after filing)
- Completed
- Oct 31, 2024 (5 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 29, 2024 | Jan 29, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 29, 2024 | Jan 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 30, 2024 | Jan 30, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 30, 2024 | Jan 30, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Feb 5, 2024 | Feb 14, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 5, 2024 | Feb 5, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 7, 2024 | Feb 7, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 8, 2024 | Feb 8, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Feb 9, 2024 | Feb 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 14, 2024 | Feb 29, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Feb 29, 2024 | Mar 7, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Feb 29, 2024 | Mar 12, 2024 | Issued Comments |
Redevelopment review Redevelopment · REDEV | Feb 29, 2024 | May 20, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 29, 2024 | May 21, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Mar 27, 2024 | Mar 27, 2024 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Mar 27, 2024 | May 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 3, 2024 | Apr 3, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 25, 2024 | Apr 26, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | May 3, 2024 | May 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2024 | May 6, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 6, 2024 | May 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 21, 2024 | May 22, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $525,000
| Name | Role | License on permit |
|---|---|---|
| Mei-Mei Chan Mei Architects | Architect | C-29350 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026