295 Sanchez St
San Francisco permit 202401304896 · Castro/Upper Market
Kitchen & bathroom renovation/remodel, selective window replacement, replace roof-guardrail glass.
- Filed
- Jan 30, 2024
- Issued
- Oct 29, 2024 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 25 stops across 4 departments
- Comments issued
- 3 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 30, 2024 | Jan 30, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jan 30, 2024 | Jan 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 30, 2024 | Jan 30, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2024 | Jan 30, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 30, 2024 | Jan 30, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2024 | Jan 30, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Feb 2, 2024 | Feb 9, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 6, 2024 | Feb 6, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 8, 2024 | Feb 8, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Feb 9, 2024 | Feb 9, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Feb 22, 2024 | Mar 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 4, 2024 | Mar 6, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Mar 6, 2024 | Aug 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 7, 2024 | Apr 18, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 7, 2024 | Apr 26, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 7, 2024 | Mar 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 1, 2024 | Jul 1, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 2, 2024 | Jul 2, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 2, 2024 | Jul 15, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 2, 2024 | Jul 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 18, 2024 | Jul 31, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 18, 2024 | Aug 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 18, 2024 | Aug 2, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 18, 2024 | Jul 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 5, 2024 | Oct 29, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Mia K Zinni Mza Ltd. | Architect | C39469 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025