762 29th Av
San Francisco permit 202402015085 · Outer Richmond
1. enlarge existing rear deck in single family residence. 2. replace and add 2 new doors and windows in existing residence facing rear yard. 3. new shear walls at upper floor at new window location. 4. remove existing detached 20sf storage shed.
- Filed
- Feb 1, 2024
- Issued
- Mar 28, 2025 (14 months after filing)
- Completed
- Oct 10, 2025 (6 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 21 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 26, 2024 | Feb 6, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 1, 2024 | Feb 1, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Feb 6, 2024 | Feb 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 6, 2024 | Feb 12, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 12, 2024 | Feb 14, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 12, 2024 | Mar 13, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 16, 2024 | Mar 27, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 16, 2024 | Mar 25, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 16, 2024 | Mar 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 27, 2024 | Mar 27, 2024 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Mar 27, 2024 | Mar 27, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 11, 2024 | Jun 17, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 11, 2024 | Jun 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 11, 2024 | Jun 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 25, 2024 | Jul 3, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 25, 2024 | Jun 27, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2024 | Jun 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2024 | Jun 27, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 8, 2024 | Jul 8, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2024 | Mar 28, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 11, 2025 | Mar 13, 2025 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $30,000
| Name | Role | License on permit |
|---|---|---|
| Ryan G Morris Morris Architecture | Payor | C33359 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025