1466 15th Av

San Francisco permit 202402025124 · Inner Sunset

AdditionFull plan reviewIssued
Street view · Mar 2022
Google Street View of 1466 15th Av, Mar 2022
Scope of work
As written on the permit application.

Partial conversion of(e)unconditioned 1st fl to(n)conditioned area.(n)conditioned areas include 1b,1ba,a music & family room and wetbar.103 sf addition to (e)garage & 106 sf rear addition to conditioned space.demolition of(e) stairs in the lgihtway.interior remodel of upper level.

Timeline
Key dates from the city record.
Filed
Apr 7, 2024
Issued
Oct 23, 2024 (7 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
29 stops across 6 departments
Comments issued
10 times, by Permit Center, Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Feb 7, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Feb 5, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Mar 13, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Mar 6, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Mar 12, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Apr 4, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Apr 2, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Apr 8, 2024Administrative

Zoning review

Planning · CP-ZOC

Apr 8, 2024Approved

Building plan review

Building Inspection · BLDG

May 28, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

Apr 24, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 17, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Sep 23, 2024Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Apr 24, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 7, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Aug 2, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Sep 4, 2024Administrative

Fire prevention review

Fire Department · SFFD

Sep 17, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 26, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 11, 2024Approved

Zoning review

Planning · CP-ZOC

Sep 10, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 26, 2024Approved

Building plan review

Building Inspection · BLDG

Sep 10, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 10, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 9, 2024Approved

Building plan review

Building Inspection · BLDG

Sep 19, 2024Approved

Building plan review

Building Inspection · BLDG

Sep 20, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

Sep 23, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Oct 23, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$535,725
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mahya Salehi Fadardi

Mahya Salehi Fadardi

ArchitectC-38610
Engin YagmurEngineer76016
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202402025124 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record