2343 Fillmore St #0
San Francisco permit 202402065323 · Pacific Heights
Renovation of existing interior garage for use in medical imaging.
- Filed
- Feb 6, 2024
- Issued
- Jul 23, 2024 (6 months after filing)
- Completed
- Feb 25, 2025 (7 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 6, 2024 | Feb 6, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 6, 2024 | Feb 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 6, 2024 | Feb 6, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 6, 2024 | Feb 6, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 6, 2024 | Feb 6, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Feb 7, 2024 | Feb 7, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Feb 7, 2024 | Feb 7, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Mar 5, 2024 | Mar 5, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 8, 2024 | Mar 8, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 8, 2024 | Mar 8, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 29, 2024 | Mar 29, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 29, 2024 | Mar 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 29, 2024 | Mar 29, 2024 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Mar 29, 2024 | Mar 29, 2024 | Approved |
Public health review Public Health · HEALTH | Mar 29, 2024 | Mar 29, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 2, 2024 | Apr 2, 2024 | Approved |
Intake Building Inspection · INTAKE | May 15, 2024 | May 15, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 16, 2024 | May 16, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 16, 2024 | May 16, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2024 | May 16, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | May 16, 2024 | May 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 16, 2024 | May 16, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | May 16, 2024 | May 16, 2024 | Approved |
Public health review Public Health · HEALTH | May 16, 2024 | May 16, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2024 | Jul 23, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $200,399
| Name | Role | License on permit |
|---|---|---|
| Neil Bernard Kaye Natoma Architects Inc. | Architect | C32794 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025