111 Pine St #0
San Francisco permit 202402075406 · Financial District/South Beach
Gr/f: tenant improvement for (e) financial banker center. no additional area of height is part of the scope. scope is limited to interior only including but not limited to partial demo of interior spaces, new finishes, new partitons and electrical.
- Filed
- Feb 7, 2024
- Issued
- Mar 27, 2024 (2 months after filing)
- Completed
- Apr 11, 2025 (12 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).
- Review stops
- 18 stops across 4 departments
- Comments issued
- 5 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 7, 2024 | Feb 7, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 7, 2024 | Feb 7, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 7, 2024 | Feb 7, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 7, 2024 | Feb 7, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 9, 2024 | Feb 9, 2024 | Approved |
Intake Building Inspection · INTAKE | Mar 5, 2024 | Mar 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 5, 2024 | Mar 5, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 5, 2024 | Mar 5, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 7, 2024 | Mar 7, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 12, 2024 | Mar 12, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | Mar 14, 2024 | Mar 14, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 14, 2024 | Mar 14, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 14, 2024 | Mar 14, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 14, 2024 | Mar 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 15, 2024 | Mar 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 15, 2024 | Mar 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 18, 2024 | Mar 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2024 | Mar 27, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $2,100,000
| Name | Role | License on permit |
|---|---|---|
| Jeffrey A Schmierer Gensler | Architect | C29750 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026