548 Delta St
San Francisco permit 202402075425 · Visitacion Valley
To accommodate a "0-5yr" childcare center. will serve approximately 60 children in 4 classrooms: 1 infant, 1 toddler, & 2 pre-k. will contain a family resource center & teacher/staff lounge. interior demolition as req. non-bearing partitions, mep, replace (e) windows & doors. (n) lula elevator,
- Filed
- Feb 7, 2024
- Issued
- Aug 12, 2024 (6 months after filing)
- Completed
- Sep 24, 2025 (13 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 48 stops across 7 departments
- Comments issued
- 14 times, by Building Inspection, Fire Department, Public Utilities, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 5, 2024 | Feb 15, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 7, 2024 | Feb 7, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Feb 9, 2024 | Feb 9, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 15, 2024 | Feb 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 15, 2024 | Mar 11, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Mar 11, 2024 | Aug 6, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 12, 2024 | Mar 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 19, 2024 | May 1, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 19, 2024 | May 17, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 19, 2024 | Apr 25, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 19, 2024 | Apr 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2024 | Mar 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2024 | Apr 8, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Mar 19, 2024 | Mar 20, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Apr 19, 2024 | May 10, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | May 13, 2024 | May 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 12, 2024 | Jun 14, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 12, 2024 | Jun 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2024 | Jun 18, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jun 12, 2024 | Jun 21, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 12, 2024 | Jun 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 12, 2024 | Jun 18, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 12, 2024 | Jul 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 12, 2024 | Jun 13, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 20, 2024 | Jun 20, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 26, 2024 | Jun 27, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2024 | Jul 9, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 1, 2024 | Jul 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2024 | Jul 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 1, 2024 | Jul 1, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2024 | Jul 8, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 1, 2024 | Jul 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2024 | Jul 3, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 3, 2024 | Jul 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 5, 2024 | Jul 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 5, 2024 | Jul 8, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 16, 2024 | Jul 22, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 16, 2024 | Jul 18, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jul 16, 2024 | Jul 16, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jul 23, 2024 | Aug 2, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 23, 2024 | Jul 24, 2024 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 23, 2024 | Jul 24, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 23, 2024 | Jul 25, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 23, 2024 | Jul 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 23, 2024 | Jul 23, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 23, 2024 | Jul 29, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 26, 2024 | Jul 26, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 5, 2024 | Aug 12, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $4,700,674
| Name | Role | License on permit |
|---|---|---|
| Ryan Joshua Jang Leddy Maytum Architects | Architect | C33368 |
| Zack Kardon Murphy Burr Curry Inc. | Engineer | C69106 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025