San Francisco permit 202402075425 · Visitacion Valley

Commercial or tenant improvementFull plan reviewComplete
Street view · Mar 2025
Google Street View of 548 Delta St, Mar 2025
Scope of work
As written on the permit application.

To accommodate a "0-5yr" childcare center. will serve approximately 60 children in 4 classrooms: 1 infant, 1 toddler, & 2 pre-k. will contain a family resource center & teacher/staff lounge. interior demolition as req. non-bearing partitions, mep, replace (e) windows & doors. (n) lula elevator,

Timeline
Key dates from the city record.
Filed
Feb 7, 2024
Issued
Aug 12, 2024 (6 months after filing)
Completed
Sep 24, 2025 (13 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
48 stops across 7 departments
Comments issued
14 times, by Building Inspection, Fire Department, Public Utilities, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Feb 15, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Feb 7, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Feb 9, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Feb 15, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Mar 11, 2024Administrative

Permit Processing Center

Building Inspection · PPC

Aug 6, 2024Administrative

Zoning review

Planning · CP-ZOC

Mar 19, 2024Approved

Building plan review

Building Inspection · BLDG

May 1, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

May 17, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 25, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Apr 19, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 26, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 8, 2024Issued Comments

Public health review

Public Health · HEALTH

Mar 20, 2024Administrative

Electrical plan review

Building Inspection · MECH-E

May 10, 2024Administrative

Electrical plan review

Building Inspection · MECH-E

May 16, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jun 14, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 21, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 18, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Jun 21, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 24, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 18, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Jul 25, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 13, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Jun 20, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 27, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 9, 2024Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jul 18, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 8, 2024Approved

Building plan review

Building Inspection · BLDG

Jul 1, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 8, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 12, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 3, 2024Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Jul 5, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jul 5, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 8, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Jul 22, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jul 18, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jul 16, 2024Administrative

Structural plan approval

Building Inspection · PAD-STR

Aug 2, 2024Approved

Urban forestry

Public Works · DPW-BUF

Jul 24, 2024Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Jul 24, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 25, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 29, 2024Approved

Building plan review

Building Inspection · BLDG

Jul 23, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 29, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Jul 26, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Aug 12, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$4,700,674
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Ryan Joshua Jang

Leddy Maytum Architects

ArchitectC33368
Zack Kardon

Murphy Burr Curry Inc.

EngineerC69106
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202402075425 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record