740 Tennessee St
San Francisco permit 202402125716 · Potrero Hill
To comply w/motion 0474:remove mechanical, electrical & plumbing equipment, conduit & pipes at north yard & relocate to interior. relocate outdoor heat pump units to roof deck. reduce & relocate elec. meters at north yard in enclosure. relocate wall & door at ground floor stair to basement.
- Filed
- Feb 12, 2024
- Issued
- Mar 7, 2024 (within 1 month of filing)
- Completed
- Mar 19, 2026 (24 months after issuance)
- Review stops
- 19 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Feb 12, 2024 | Feb 12, 2024 | Administrative |
Intake Building Inspection · INTAKE | Feb 12, 2024 | Feb 12, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 13, 2024 | Feb 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 13, 2024 | Feb 13, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 13, 2024 | Feb 13, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 13, 2024 | Feb 13, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 13, 2024 | Feb 13, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 13, 2024 | Feb 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2024 | Feb 13, 2024 | Approved |
Public health review Public Health · HEALTH | Feb 13, 2024 | Feb 13, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 20, 2024 | Feb 20, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Feb 20, 2024 | Feb 20, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 21, 2024 | Feb 21, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 21, 2024 | Feb 21, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 22, 2024 | Feb 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 22, 2024 | Feb 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 5, 2024 | Mar 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 5, 2024 | Mar 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2024 | Mar 7, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| P Vincent Gonzaga Vincent Gonzaga Architect | Architect | C33614 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026