645 Congo St
San Francisco permit 202402166034 · West of Twin Peaks
Add (n) 6 soldier piles with wood lagging at north side elevation.
- Filed
- Apr 8, 2024
- Issued
- Jan 24, 2025 (10 months after filing)
- Completed
- Feb 13, 2026 (13 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 25 stops across 4 departments
- Comments issued
- 8 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 16, 2024 | Feb 16, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 20, 2024 | Feb 20, 2024 | Approved |
Intake Building Inspection · INTAKE | Feb 22, 2024 | Feb 22, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 26, 2024 | Feb 26, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Feb 29, 2024 | Mar 13, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 4, 2024 | Mar 4, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 5, 2024 | Mar 5, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Mar 7, 2024 | Mar 7, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 12, 2024 | Mar 12, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 13, 2024 | Mar 13, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 15, 2024 | Mar 20, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 20, 2024 | Mar 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 20, 2024 | Apr 8, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Apr 8, 2024 | Apr 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 8, 2024 | Jun 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 8, 2024 | Apr 15, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 8, 2024 | Jan 14, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 3, 2024 | Oct 3, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 3, 2024 | Oct 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 24, 2024 | Oct 25, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 9, 2024 | Dec 19, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 8, 2025 | Jan 8, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 9, 2025 | Jan 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2025 | Jan 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 14, 2025 | Jan 24, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $160,000
| Name | Role | License on permit |
|---|---|---|
| Behruz Vahdani-Sanavi Us Prime Contractor Inc. | Engineer | C35605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2014