Add (n) 6 soldier piles with wood lagging at north side elevation.

Timeline
Key dates from the city record.
Filed
Apr 8, 2024
Issued
Jan 24, 2025 (10 months after filing)
Completed
Feb 13, 2026 (13 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
25 stops across 4 departments
Comments issued
8 times, by Permit Center, Building Inspection
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Feb 16, 2024Administrative

Zoning review

Planning · CP-ZOC

Feb 20, 2024Approved

Intake

Building Inspection · INTAKE

Feb 22, 2024Administrative

Zoning review

Planning · CP-ZOC

Feb 26, 2024Approved

Permit Center

Permit Center · PERMIT-CTR

Mar 13, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Mar 4, 2024Not Applicable

Electrical pre-screening

Building Inspection · PRE-MECH-E

Mar 5, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Mar 7, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Mar 12, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Mar 13, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Mar 20, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Mar 20, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Apr 8, 2024Administrative

Zoning review

Planning · CP-ZOC

Apr 8, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 7, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 15, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jan 14, 2025Administrative

Building plan review

Building Inspection · BLDG

Oct 3, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Oct 3, 2024Administrative

Building plan review

Building Inspection · BLDG

Oct 25, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Dec 19, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jan 8, 2025Approved

Zoning review

Planning · CP-ZOC

Jan 13, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jan 10, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jan 24, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$160,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Behruz Vahdani-Sanavi

Us Prime Contractor Inc.

EngineerC35605
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202402166034 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record