2776 Broadway
San Francisco permit 202402166040 · Pacific Heights
Minor additions on n & s 10ft horizontal but not exceed (e) roof ht. add 167sf on 3rd lvl.n/s installation of moment frame.additions tie into (e) buyilding structure and there will be no foundatoins or excavation. interior work within all 3 floors.
- Filed
- May 17, 2024
- Issued
- Sep 6, 2024 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 16, 2024 | Feb 16, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 16, 2024 | Feb 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 18, 2024 | Mar 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 18, 2024 | Mar 18, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | May 6, 2024 | May 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 8, 2024 | May 17, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | May 14, 2024 | May 14, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 15, 2024 | May 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 17, 2024 | May 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 17, 2024 | Jul 9, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 17, 2024 | Jun 21, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 17, 2024 | May 23, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 17, 2024 | Sep 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 12, 2024 | Aug 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 21, 2024 | Aug 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 21, 2024 | Aug 21, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 23, 2024 | Aug 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 26, 2024 | Aug 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 26, 2024 | Aug 27, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 26, 2024 | Aug 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 27, 2024 | Aug 27, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 3, 2024 | Sep 6, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $275,000
| Name | Role | License on permit |
|---|---|---|
| Joshua Sawyer Cohn C A Architects | Architect | C23410 |
| Chris Warner Zfa Structural Enginers | Engineer | S-4613 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025