As written on the permit application.

Develope (e) utility basement of the (e) single family dwelling into an attached adu per state program:install (n) kitchen with a living,dining,kitchen,room.install (n) bedroom with full bath.install detached pre-fab 4'6" x 5' x 6'ht utility shed at (e) exterior concrete patio.

Timeline
Key dates from the city record.
Filed
Feb 20, 2024
Issued
Sep 9, 2024 (7 months after filing)
Completed
Feb 18, 2026 (17 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
31 stops across 5 departments
Comments issued
6 times, by Planning, Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Feb 27, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Feb 26, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Feb 27, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Feb 27, 2024Not Applicable

Central Permit Bureau

Building Inspection · CPB

Feb 28, 2024Administrative

Zoning review

Planning · CP-ZOC

Apr 10, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Mar 8, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 7, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 18, 2024Approved

Urban forestry

Public Works · DPW-BUF

Mar 27, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 1, 2024Approved

Permit Processing Center

Building Inspection · PPC

Aug 26, 2024Administrative

Structural plan approval

Building Inspection · PAD-STR

Mar 7, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

May 22, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Jul 9, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 10, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 17, 2024Approved

Urban forestry

Public Works · DPW-BUF

Jul 16, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jun 6, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 14, 2024Approved

Zoning review

Planning · CP-ZOC

Jul 23, 2024Approved

Urban forestry

Public Works · DPW-BUF

Jul 29, 2024Approved

Development fee collection

Building Inspection · DFCU

Jul 30, 2024Administrative

Zoning review

Planning · CP-ZOC

Aug 22, 2024Approved

Building plan review

Building Inspection · BLDG

Aug 12, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 16, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Aug 5, 2024Approved

Urban forestry

Public Works · DPW-BUF

Aug 21, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 7, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 26, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Sep 9, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$105,953
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Van Thai Ly

Van T. Ly & Associataes

ArchitectC25710
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202402206131 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record