2 B Lupine Av
San Francisco permit 202402206131 · Presidio Heights
Develope (e) utility basement of the (e) single family dwelling into an attached adu per state program:install (n) kitchen with a living,dining,kitchen,room.install (n) bedroom with full bath.install detached pre-fab 4'6" x 5' x 6'ht utility shed at (e) exterior concrete patio.
- Filed
- Feb 20, 2024
- Issued
- Sep 9, 2024 (7 months after filing)
- Completed
- Feb 18, 2026 (17 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 31 stops across 5 departments
- Comments issued
- 6 times, by Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 16, 2024 | Feb 27, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 26, 2024 | Feb 26, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Feb 27, 2024 | Feb 27, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 27, 2024 | Feb 27, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2024 | Feb 28, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 28, 2024 | Apr 10, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 28, 2024 | Mar 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 28, 2024 | Mar 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 28, 2024 | Mar 18, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 28, 2024 | Mar 27, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 28, 2024 | Mar 1, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 28, 2024 | Aug 26, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Mar 1, 2024 | Mar 7, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2024 | May 22, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 5, 2024 | Jul 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 5, 2024 | Jun 10, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2024 | Jun 17, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 5, 2024 | Jul 16, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 5, 2024 | Jun 6, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 5, 2024 | Jun 14, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 23, 2024 | Jul 23, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 29, 2024 | Jul 29, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jul 30, 2024 | Jul 30, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Aug 2, 2024 | Aug 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 2, 2024 | Aug 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 2, 2024 | Aug 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 2, 2024 | Aug 5, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 2, 2024 | Aug 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 2, 2024 | Aug 7, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 26, 2024 | Aug 26, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 26, 2024 | Sep 9, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $105,953
| Name | Role | License on permit |
|---|---|---|
| Van Thai Ly Van T. Ly & Associataes | Architect | C25710 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026