San Francisco permit 202402216312 · Pacific Heights

AdditionFull plan reviewIssued
Street view · Dec 2024
Google Street View of 2111 Franklin St #10, Dec 2024
Scope of work
As written on the permit application.

Unit 10: 208sf horizontal addition to an (e) 5/f single level condo. the enclosure of an (e) 25sf exterior balcony to conditioned space and a minor remodel of the (e) primary bathroom, powder room and laundry area.

Timeline
Key dates from the city record.
Filed
Mar 27, 2024
Issued
Aug 26, 2024 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 5 departments
Comments issued
4 times, by Permit Center, Building Inspection, Public Utilities
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Mar 4, 2024Issued Comments

Central Permit Bureau

Building Inspection · CPB

Mar 28, 2024Administrative

Building pre-screening

Building Inspection · PRE-BLDG

Mar 1, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Mar 1, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Mar 27, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Mar 22, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Mar 26, 2024Approved

Zoning review

Planning · CP-ZOC

Apr 1, 2024Approved

Building plan review

Building Inspection · BLDG

May 24, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 22, 2024Approved

Fire prevention review

Fire Department · SFFD

Apr 18, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 10, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Aug 23, 2024Administrative

Fire prevention review

Fire Department · SFFD

Apr 18, 2024Administrative

Public Utilities Commission review

Public Utilities · SFPUC

May 2, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 26, 2024Approved

Building plan review

Building Inspection · BLDG

Jul 10, 2024Approved

Zoning review

Planning · CP-ZOC

Jul 10, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 11, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 11, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Aug 26, 2024Administrative

Building Inspection

417-86

Aug 23, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$109,850
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Gyo Max ObataArchitectC-38332
Kathryn Briggs

Base Design

EngineerS-5732
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202402216312 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record