429 Castro St
San Francisco permit 202402296854 · Castro/Upper Market
Priority: renovation & addition to historic castro theater.floor system w/an access. path to the platform,(n)organ lift & organ cover,(n)hvac system,thetrical system upgrades & electrical,fire alarm, lighting & plumbing upgrades.addition installed over(e)foundations includes(n)dressing rms & restrms
- Filed
- Feb 29, 2024
- Issued
- Oct 10, 2024 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 43 stops across 7 departments
- Comments issued
- 25 times, by Building Inspection, Fire Department, Public Works, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 28, 2024 | Mar 8, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 4, 2024 | Mar 4, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 4, 2024 | Mar 4, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 7, 2024 | Mar 7, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 7, 2024 | Mar 7, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 12, 2024 | Mar 14, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 15, 2024 | Sep 16, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 15, 2024 | Oct 4, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 19, 2024 | May 2, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 19, 2024 | May 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 19, 2024 | May 9, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 19, 2024 | Mar 29, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2024 | Mar 21, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2024 | Mar 28, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 24, 2024 | Apr 26, 2024 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | May 2, 2024 | May 2, 2024 | Approved |
Public health review Public Health · HEALTH | May 3, 2024 | May 14, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 7, 2024 | Jun 21, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 7, 2024 | Jun 7, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 12, 2024 | Jun 12, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 20, 2024 | Jun 28, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 27, 2024 | Jun 28, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 27, 2024 | Jul 5, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 11, 2024 | Jul 12, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 16, 2024 | Jul 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 17, 2024 | Jul 29, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 18, 2024 | Jul 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 23, 2024 | Jul 23, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 25, 2024 | Aug 6, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 1, 2024 | Aug 5, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 13, 2024 | Aug 14, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 14, 2024 | Aug 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 23, 2024 | Sep 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 27, 2024 | Aug 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 28, 2024 | Sep 4, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 29, 2024 | Aug 29, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 29, 2024 | Aug 30, 2024 | Approved-Stipulated |
Public health review Public Health · HEALTH | Aug 29, 2024 | Aug 29, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 3, 2024 | Sep 3, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 10, 2024 | Sep 10, 2024 | Approved |
Public health review Public Health · HEALTH | Sep 13, 2024 | Sep 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 4, 2024 | Oct 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2024 | Oct 10, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $5,788,309
| Name | Role | License on permit |
|---|---|---|
| Christopher Scott Wasney Caw Architects, Inc | Architect | C-22197 |
| David Clifton Mar Mar Structural Design | Engineer | S-3951 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022