2293 Powell St
San Francisco permit 202403016912 · North Beach
Installation of new dcfc ev charging station.installationg of (1) new switchboard, 5 ac-dc cabinets, 19 charging posts and associated ada acess features.
- Filed
- Apr 30, 2024
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 27 stops across 6 departments
- Comments issued
- 11 times, by Permit Center, Building Inspection, Public Works, Public Health, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 29, 2024 | Mar 11, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Mar 1, 2024 | Apr 30, 2024 | Administrative |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 5, 2024 | Mar 5, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 6, 2024 | Mar 6, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Mar 8, 2024 | Mar 8, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 25, 2024 | Apr 3, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 26, 2024 | Mar 26, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 3, 2024 | Apr 3, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 4, 2024 | Apr 16, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 10, 2024 | Apr 10, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 30, 2024 | May 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 30, 2024 | May 22, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 30, 2024 | Jun 7, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 30, 2024 | May 13, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 30, 2024 | May 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 30, 2024 | May 3, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 30, 2024 | In progress | — |
Public health review Public Health · HEALTH | May 23, 2024 | May 24, 2024 | Not Applicable |
Public Health HEALTH-MH | May 28, 2024 | May 28, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 19, 2024 | Jul 19, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 13, 2024 | Aug 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Public Health HEALTH-MH | — | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Withdrawn
- Estimated cost
- $640,000
| Name | Role | License on permit |
|---|---|---|
| Ahsanullah Kushkaki | Engineer | C-59045 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025