255 Sutter St
San Francisco permit 202403046976 · Financial District/South Beach
Facade rehabilitation. terra cotta repair, including patching and repointing. wood window and metal decoring painting. concrete parapet repair.
- Filed
- Mar 4, 2024
- Issued
- Sep 4, 2024 (6 months after filing)
- Completed
- Sep 25, 2025 (13 months after issuance)
- Review stops
- 14 stops across 5 departments
- Comments issued
- Twice, by Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 4, 2024 | Mar 4, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 4, 2024 | Mar 4, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 6, 2024 | Apr 17, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 22, 2024 | Apr 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 1, 2024 | May 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 1, 2024 | May 1, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 1, 2024 | May 1, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 1, 2024 | May 1, 2024 | Approved |
Intake Building Inspection · INTAKE | Sep 4, 2024 | Sep 4, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 4, 2024 | Sep 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 4, 2024 | Sep 4, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 4, 2024 | Sep 4, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 4, 2024 | Sep 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2024 | Sep 4, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Jacqui Atiya Hogans | Architect | C39948 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025