San Francisco permit 202403057113 · Mission

Commercial or tenant improvementOver-the-counter, with plansIssued
Street view · Sep 2026
Google Street View of 1419 Bryant St, Sep 2026
Scope of work
As written on the permit application.

Build out of unoccupied 3/f shell spaces, including selective demo and reconfiguration of (e) lighting, plumbing, hvac and fire sprinklers for tie-in to (e) building systems. 3/f north shell space to include new storage, restrooms, lockers, conference room and electrical room. south shell to include

Timeline
Key dates from the city record.
Filed
Mar 5, 2024
Issued
Mar 26, 2025 (13 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2024 were typically issued within 1 month (median of 4,701 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
21 stops across 6 departments
Comments issued
Once, by Building Inspection
Review stopFinishedResult

Public Works disability access review

Public Works · PW-DAC

Feb 29, 2024Approved

Intake

Building Inspection · INTAKE

Mar 5, 2024Administrative

Zoning review

Planning · CP-ZOC

Mar 5, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 6, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Mar 6, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 12, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Mar 13, 2024Approved

Fire prevention review

Fire Department · SFFD

Mar 13, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 13, 2024Approved

Public health review

Public Health · HEALTH

Mar 14, 2024Administrative

Public health food review

Public Health · HEALTH-FD

Mar 19, 2024Not Applicable

Intake

Building Inspection · INTAKE

Nov 12, 2024Administrative

Building plan review

Building Inspection · BLDG

Nov 12, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 12, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Nov 12, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 12, 2024Approved

Zoning review

Planning · CP-ZOC

Dec 3, 2024Approved

Electrical plan review

Building Inspection · MECH-E

Dec 3, 2024Approved

Fire prevention review

Fire Department · SFFD

Dec 3, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 25, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Mar 26, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
OTC alterations permit
Status
Issued
Estimated cost
$2,924,895
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Patricia Isabel Solis

Ccsf Dpw

ArchitectC29354
Raymond Lui

Dpw.Infrastrucure Design

EngineerS-4094
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202403057113 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record