CheckMyDesigner

6 Richards Cr

San Francisco permit 202403117535 · Bayview Hunters Point

New buildingFull plan reviewFiled
Street view · Mar 2019
Google Street View of 6 Richards Cr, Mar 2019
Scope of work
As written on the permit application.

New 1000 sf rear detached adu (2-story all electric), 1-kitchen, 2-bedrooms, 2-bathrooms, type v-b.

Timeline
Key dates from the city record.
Filed
Nov 4, 2024
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
56 stops across 6 departments
Comments issued
22 times, by Permit Center, Building Inspection, Planning, Fire Department, Public Utilities, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Mar 19, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Mar 11, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Mar 12, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Mar 18, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Sep 4, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Aug 28, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Aug 29, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Aug 30, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Sep 20, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Sep 13, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Sep 20, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Nov 5, 2024Administrative

Zoning review

Planning · CP-ZOC

Dec 17, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Dec 2, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Dec 6, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 14, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 5, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Nov 6, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 22, 2024Approved

Permit Processing Center

Building Inspection · PPC

In progressAdministrative

Mechanical and energy plan review

Building Inspection · MECH

Nov 14, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Feb 25, 2025Approved

Zoning review

Planning · CP-ZOC

Mar 25, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 24, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 11, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 19, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Mar 20, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 26, 2025Approved

Zoning review

Planning · CP-ZOC

Sep 12, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Sep 25, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 9, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Oct 2, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

Oct 20, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 30, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Sep 29, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 15, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Oct 22, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 23, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Oct 22, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 20, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Oct 20, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 23, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 18, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 19, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 25, 2026Approved

Zoning review

Planning · CP-ZOC

Mar 30, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 1, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Mar 30, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 3, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Apr 1, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 2, 2026Approved

Development fee collection

Building Inspection · DFCU

Apr 3, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

In progress—

Urban forestry

Public Works · DPW-BUF

Apr 27, 2026Issued Comments

Address verification

Building Inspection · ADDR

In progress—

Urban forestry

Public Works · DPW-BUF

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Filed
Estimated cost
$337,767
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Lei Zheng

Cecilia Home

EngineerC69809
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202403117535 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record