1349 Taraval St
San Francisco permit 202403137707 · Sunset/Parkside
At the ground floor -change of use from office to child care center (6m-4 years old). new child restroom. new crib room. mep submittal deferred
- Filed
- Jul 11, 2024
- Issued
- Mar 5, 2025 (8 months after filing)
- Completed
- Jun 23, 2025 (4 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 33 stops across 7 departments
- Comments issued
- 13 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 12, 2024 | Mar 19, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 13, 2024 | Mar 13, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 13, 2024 | Mar 13, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2024 | Jul 11, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Mar 14, 2024 | Mar 14, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 29, 2024 | Apr 5, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jun 18, 2024 | Jun 18, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jun 27, 2024 | Jul 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 11, 2024 | Jul 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 11, 2024 | Jul 23, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 11, 2024 | Jul 30, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 11, 2024 | Aug 21, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 11, 2024 | Jul 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 11, 2024 | Jul 25, 2024 | Approved |
Public health review Public Health · HEALTH | Jul 11, 2024 | Jul 11, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Jul 11, 2024 | Feb 14, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 4, 2024 | Oct 22, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 4, 2024 | Oct 18, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 4, 2024 | Oct 9, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 4, 2024 | Oct 10, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 4, 2024 | Nov 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 4, 2024 | Oct 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 7, 2024 | Nov 13, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2024 | Nov 12, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 7, 2024 | Nov 14, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2024 | Nov 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2024 | Nov 14, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 27, 2024 | Dec 27, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 29, 2025 | Jan 31, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 29, 2025 | Feb 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 5, 2025 | Feb 5, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Feb 10, 2025 | Feb 10, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 14, 2025 | Mar 5, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $40,000
| Name | Role | License on permit |
|---|---|---|
| John C Lee John Lee | Architect | C6896 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026