221 Main St
San Francisco permit 202403147834 · Financial District/South Beach
Work on ground fl,consists of interior demo of non-structrural elements indlcuding but not necessarily limited to,interior partitions,doors,finishes,ceilings,lighting,mech & elec outlets & switches.addition of(n)gender neutral restrooms.
- Filed
- Apr 10, 2024
- Issued
- Aug 19, 2024 (4 months after filing)
- Completed
- May 14, 2025 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 30 stops across 6 departments
- Comments issued
- 9 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 13, 2024 | Mar 21, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 14, 2024 | Mar 14, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Mar 19, 2024 | Mar 19, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 20, 2024 | Mar 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 22, 2024 | Apr 10, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Apr 10, 2024 | Apr 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2024 | May 17, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2024 | May 10, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 10, 2024 | May 1, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2024 | Apr 15, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2024 | Apr 19, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 10, 2024 | Aug 13, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Apr 11, 2024 | Apr 16, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | May 4, 2024 | May 4, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 17, 2024 | May 17, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 30, 2024 | May 30, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 14, 2024 | Jun 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 17, 2024 | Jun 17, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 18, 2024 | Jun 18, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 20, 2024 | Jun 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 24, 2024 | Jun 24, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2024 | Aug 5, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 6, 2024 | Aug 6, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 6, 2024 | Aug 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 6, 2024 | Aug 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 6, 2024 | Aug 13, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 6, 2024 | Aug 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 6, 2024 | Aug 7, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 6, 2024 | Aug 7, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 13, 2024 | Aug 19, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,505,065
| Name | Role | License on permit |
|---|---|---|
| Scott Eugene Clement Revel Architecture & Design | Architect | C36455 |
| Alan Robinson Tuan + Robison | Engineer | S3971 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023