Scope of work
As written on the permit application.

Excavate existing crawl spaces withink existing bldg basement garage to match existing garage floor level. new foundation and structural framing as reqiuired. no change to the conditioned spaces or exterior of the residence. mech, elect and plumb under sep permit.

Timeline
Key dates from the city record.
Filed
Apr 8, 2024
Issued
Mar 28, 2025 (12 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 4 departments
Comments issued
4 times, by Building Inspection
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Mar 15, 2024Administrative

Zoning review

Planning · CP-ZOC

Mar 15, 2024Approved

Intake

Building Inspection · INTAKE

Mar 20, 2024Administrative

Building plan review

Building Inspection · BLDG

Mar 20, 2024Administrative

Permit Center

Permit Center · PERMIT-CTR

Apr 5, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Apr 9, 2024Administrative

Electrical pre-screening

Building Inspection · PRE-MECH-E

Apr 3, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Apr 4, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Apr 4, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 20, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 24, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 3, 2024Approved

Permit Processing Center

Building Inspection · PPC

Mar 18, 2025Administrative

Electrical plan review

Building Inspection · MECH-E

Apr 24, 2024Not Applicable

Building plan review

Building Inspection · BLDG

Jun 20, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Dec 2, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Feb 7, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Feb 20, 2025Approved

Zoning review

Planning · CP-ZOC

Mar 12, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 17, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 14, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Mar 28, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$300,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Thomas Abraham Ziv

Ziv Potampa

ArchitectC18897
David Benjamin Yadegar

David Yadegar, Pe

EngineerC73922
Sources