30 Presidio Tr
San Francisco permit 202403157975 · Inner Richmond
Excavate existing crawl spaces withink existing bldg basement garage to match existing garage floor level. new foundation and structural framing as reqiuired. no change to the conditioned spaces or exterior of the residence. mech, elect and plumb under sep permit.
- Filed
- Apr 8, 2024
- Issued
- Mar 28, 2025 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 15, 2024 | Mar 15, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 15, 2024 | Mar 15, 2024 | Approved |
Intake Building Inspection · INTAKE | Mar 20, 2024 | Mar 20, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 20, 2024 | Mar 20, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Apr 2, 2024 | Apr 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2024 | Apr 9, 2024 | Administrative |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 3, 2024 | Apr 3, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Apr 4, 2024 | Apr 4, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 4, 2024 | Apr 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 9, 2024 | Jun 20, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 9, 2024 | Apr 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 9, 2024 | May 3, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 9, 2024 | Mar 18, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Apr 24, 2024 | Apr 24, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Jun 20, 2024 | Jun 20, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 27, 2024 | Dec 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 7, 2025 | Feb 7, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 11, 2025 | Feb 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 11, 2025 | Mar 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2025 | Mar 17, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2025 | Mar 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 18, 2025 | Mar 28, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Thomas Abraham Ziv Ziv Potampa | Architect | C18897 |
| David Benjamin Yadegar David Yadegar, Pe | Engineer | C73922 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025