22 Valley St
San Francisco permit 202403198162 · Noe Valley
Interior remodel of upper lvl renovation of kitchen, relocate bathroom, 2 new bathrooms, rlocated laundry, select new or alter windows & doors. replace rear roof. associated electrical & plumbing. new duct heat pump & heat pump hot water heater
- Filed
- Apr 7, 2024
- Issued
- Aug 8, 2024 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 19 stops across 4 departments
- Comments issued
- 5 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 19, 2024 | Mar 19, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 19, 2024 | Mar 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 21, 2024 | Mar 21, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Mar 23, 2024 | Apr 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 25, 2024 | Apr 8, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Apr 1, 2024 | Apr 1, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 2, 2024 | Apr 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 8, 2024 | Jun 7, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 8, 2024 | May 1, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 8, 2024 | Apr 19, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 8, 2024 | Jul 30, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jun 28, 2024 | Jul 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 9, 2024 | Jul 10, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2024 | Jul 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 16, 2024 | Jul 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 24, 2024 | Aug 8, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Jul 24, 2024 | Jul 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2024 | Jul 30, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2024 | Aug 8, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $430,405
| Name | Role | License on permit |
|---|---|---|
| Charles Andrew Sang-Ho Lee Charles Lee Architects | Architect | C35189 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2021